Premier African Minerals (PREM) H2 2023 earnings summary
Event summary combining transcript, slides, and related documents.
H2 2023 earnings summary
31 Mar, 2026Executive summary
Completed Zulu Lithium and Tantalum Project plant, but faced major operational setbacks due to ore sorting and milling deficiencies, delaying production and impacting cash flows.
Raised $17.542 million in net funds through share issues to support Zulu commissioning and development.
RHA Tungsten mine remains fully impaired and under care and maintenance, with no new funding since July 2019.
Focus remains on stabilising Zulu operations and exploring value in other assets, including manganese and gold projects.
Financial highlights
Reported a loss before and after tax of $20.813 million for 2023, compared to a $5.803 million loss in 2022.
Gross trading loss before depreciation and amortisation was $3.805 million (2022: $nil).
Administrative expenses rose to $10.645 million (2022: $4.622 million).
Finance costs increased to $5.818 million (2022: $nil).
Total comprehensive loss for the year was $21.312 million (2022: $13.646 million).
No dividend recommended for the year.
Cash and cash equivalents at year-end were $0.542 million (2022: $9.627 million).
Investment in property, plant, and equipment reached $53.234 million (2022: $35.997 million).
Outlook and guidance
Zulu plant expected to reach design throughput and recovery targets after installation of a new scrubber unit in July 2024.
Anticipates increased production capacity and longer mine life at Zulu based on updated resource estimates.
Plans to address RHA, MNH, and Vortex project statuses and seek high-value exploration targets.
Ongoing support from offtake and prepayment partner, with flexibility to seek alternative funding.
Latest events from Premier African Minerals
- Special resolutions for share issuance passed; focus remains on plant optimization and funding.PREM
AGM 20241 Apr 2026 - All resolutions passed; Zulu plant upgrades and cost-saving initiatives progressing.PREM
AGM 202531 Mar 2026 - Zulu Project in Zimbabwe is now producing lithium concentrate, driving growth and expansion.PREM
Corporate presentation31 Mar 2026 - H1 2024 saw a $12M loss, Zulu project delays, and urgent funding needs for continued operations.PREM
H1 202431 Mar 2026 - Comprehensive loss narrowed to $20.2M; Zulu commissioning and funding remain critical.PREM
H2 202431 Mar 2026 - Losses narrowed as Zulu optimisation advanced, but funding and liquidity risks remain.PREM
H1 202531 Mar 2026