PSP Projects (PSPPROJECT) Q4 20/21 earnings summary
Event summary combining transcript, slides, and related documents.
Q4 20/21 earnings summary
23 Oct, 2026Executive summary
FY21 operations were hit by COVID-19 disruptions, but quarterly revenue, EBITDA and PAT recovered to YoY growth of 10%, 23% and 20%, respectively, in Q4.
FY21 work orders reached ₹2,441.17 crore; the March 31 order book was a record ₹4,120.97 crore across 42 projects, supporting revenue visibility.
Geographic reach expanded to six states, with 61% of the order book outside Gujarat; government projects, including seven UP medical colleges and hospitals, drove diversification.
Financial highlights
Standalone revenue from operations fell 17% YoY to ₹1,240.86 crore; EBITDA declined 29% to ₹134.81 crore.
Standalone PBT after exceptional items was ₹108.66 crore versus ₹174.42 crore; PAT was ₹80.79 crore versus ₹129.26 crore.
Consolidated revenue was ₹1,240.86 crore; net profit attributable to owners was ₹81.53 crore versus ₹128.48 crore in FY20.
Standalone operating cash flow increased to ₹70.83 crore from ₹19.04 crore; closing cash and cash equivalents were ₹115.33 crore.
Outlook and guidance
Management expects the record order book, order pipeline and execution capabilities to support future growth and strong order flows over the next couple of years.
Remaining performance obligations were ₹4,120.97 crore, with tentative execution of ₹1,867.58 crore in FY22, ₹1,882.75 crore in FY23 and ₹370.64 crore in FY24.
Precast plant Phase I capacity is 1 million sq. ft.; full operational capacity is expected to reach 3 million sq. ft. annually.
Priorities include larger projects, balanced sector and geographic mix, technology adoption, customer relationships and workforce capability-building.
Latest events from PSP Projects
- FY22 growth accelerated as precast investment and a ₹4,324 crore order book scaled the platform.PSPPROJECT
Q4 21/22 - Profitability rose sharply despite lower reported revenue; IPO proceeds targeted working capital and capex.PSPPROJECT
Q4 16/17 - Record FY18 growth and a ₹2,644 cr order book underpin 40% FY19 revenue guidance.PSPPROJECT
Q4 17/18 - Record FY20 results and a ₹3,073.56 crore order book meet near-term COVID-19 disruption.PSPPROJECT
Q4 19/20 - Record earnings and a ₹2,978 crore order book underpin growth, with SDB execution the key swing factor.PSPPROJECT
Q4 18/19 - Revenue grew, margins contracted, and a ₹5,052 crore order book supports FY24 growth.PSPPROJECT
Q4 22/23 - Record growth and order visibility, tempered by weaker profit and cash generation.PSPPROJECT
Q4 23/24 - Q3 FY25 profit plunged on project delays, but Adani partnership and order book support FY26 growth.PSPPROJECT
Q3 24/25 - Q1 revenue up 65% YoY; order book at INR 13,245 crore; margins and EPS surged.PSPPROJECT
Q1 26/27