23 Jun, 2025Strategic focus and objectives
Prioritizing development of the Kiniero Gold Project in Guinea, with plans to spin out the Nampala operation in Mali to focus resources on Kiniero.
Targeting first gold production at Kiniero by Q4 2025, with construction of a new 3Mtpa CIL plant underway and all permits secured.
Aiming to list on the ASX and delist from TSX-V, with a new management team and board appointed to drive execution.
Committed to responsible mining practices and maintaining a disciplined buy-and-build approach to become a mid-tier producer.
Exploration strategy focuses on expanding resource inventory and near-mine oxide production.
Kiniero project highlights and financials
Kiniero has an indicated resource of 1.48Moz gold and a probable reserve of 1Moz, with a 9.5-year mine life based on the June 2023 DFS.
Projected annual production is over 150koz at a low AISC, with a forecast AISC of $980/oz and average annual EBITDA of $72–108 million.
Pre-production capex is $160 million, with an NPV5% of $257–453 million and IRR of 42–67% at gold prices of $1,850–2,300/oz.
Over $55 million invested to date, with FEED work completed and all major permits in place.
Project financing package targeted for close in 2H 2024, with debt drawdown and construction milestones mapped to deliver first gold by Q4 2025.
Exploration and resource growth
Kiniero district offers significant exploration upside, with resources drilled only to shallow depths and most drilling ending in mineralization.
Mansounia addition brings an indicated resource of 303koz at 1.00g/t, with infill drilling ongoing and 80% of resources less than 70m from surface.
High historical resource conversion ratio (70% M&I), with discovery costs under $10/oz and a 23% increase in indicated resources in the latest update.
Long-term exploration targets in largely unexplored northern blocks, with soil samples pending and proximity to major deposits like Bankan.
Near-mine exploration at Sabali, Mansounia, and SGA Complex continues to add economic oxide ounces to the mine plan.
Latest events from Robex Resources
- First gold pour targeted for year-end, with robust financing and major exploration upside.RBX
2025 Precious Metals Summit - Beaver Creek3 Feb 2026 - Gold project in Guinea accelerates toward 2025 production with robust team and new ASX listing.RBX
2024 Precious Metals Summit Beaver Creek20 Jan 2026 - Arrangement resolution passed with 94.54% approval at the virtual shareholders' meeting.RBX
EGM 202530 Dec 2025 - Merger forms Guinea's largest gold producer with 9Moz+ resources and 400koz+ output by 2029.RBX
M&A Announcement6 Oct 2025 - Kiniero project on track for first gold in December 2025, backed by strong execution and financing.RBX
Investor Presentation23 Jun 2025 - Gold sales surged on higher prices, but losses persisted as Kiniéro project advances toward production.RBX
Q1 202516 Jun 2025 - Operating income up, net loss driven by one-time items; Kiniero project on schedule.RBX
Q3 202413 Jun 2025 - Revenue up 35% in Q2, but a $43M tax hit drove a net loss; Kiniéro funding secured.RBX
Q2 202413 Jun 2025 - Revenue rose on higher gold prices, but a tax settlement led to a net loss for 2024.RBX