Rockhopper Exploration (RKH) H1 2026 earnings summary
Event summary combining transcript, slides, and related documents.
H1 2026 earnings summary
30 Sep, 2026Executive summary
NDA 1 project sanctioned in late 2025, fully funded, targeting first oil in Q1 2028; manufacturing and on-island work progressing, with drilling to start early 2027.
Second FPSO purchased for CDA, aiming to increase total production to ~180,000 bbls/d; FID for CDA targeted in H1 2028, first oil possible in 2030.
Updated reserves and resources report shows 2P reserves of 110mmbbls and 2C resources of 219mmbbls; post-tax NPV10 at 2P+2C level increased by $0.79bn to $2.95bn.
Capital raise of $200 million completed, funding operations through mid-2028, including NDA 1, CDA, and exploration.
Board strengthened with new CFO and Non-Executive Director; Italian asset disposal pending final regulatory approval.
Financial highlights
Loss after tax for H1 2026 was $3.4 million, a significant improvement from $51.0 million loss in H1 2025.
Administrative expenses flat at $2.5 million; finance income rose to $2.2 million, finance expenses increased to $3.1 million.
Cash and term deposits at 30 June 2026 were $147.0 million (down from $171.0 million at year-end 2025).
Additions to property, plant, and equipment totaled $76.3 million, mainly for NDA 1 development.
Total equity increased to $352.6 million, reflecting capital raise and share-based payments.
Outlook and guidance
Fully funded to mid-2028, with first oil from NDA 1 targeted for Q1 2028 and CDA FID readiness by mid-2028.
Exploration drilling to recommence in NFB during or after the development campaign.
Contingency funding and undrawn $350 million Senior Debt Facility provide additional liquidity.
Latest events from Rockhopper Exploration
- Sea Lion Phase 1 is fully funded, targeting first oil in 2028 with major upside potential.RKH
AGM 2026 presentation - Sea Lion Phase 1 is fully funded and on track for first oil in Q1 2028.RKH
H2 2025 - Sea Lion advances, Ombrina Mare monetised, and board succession completed amid key risks.RKH
AGM 2024 - Sea Lion project nears FID with new financing as Italian exit reduces liabilities.RKH
AGM 2025 - $150 million capital raise secures full funding for Sea Lion Phase 1 FID and contingencies.RKH
Investor presentation - Sea Lion project nears FID with robust funding, phased development, and strong financial backing.RKH
Corporate presentation - Sea Lion project advanced, Ombrina Mare monetisation agreed, strong cash, key risks remain.RKH
H2 2023 - H1 2024 profit of $16.5 million reflects Award monetisation and strong Sea Lion project progress.RKH
H1 2024 - 2024 profit surged to $47.6 million as Sea Lion financing advanced and Italian assets exited.RKH
H2 2024