Net revenues for Jan–Sep 2025 were MSEK 28.9, a sharp decline from MSEK 164.7 year-over-year, mainly due to lower milestone payments from the Uddevalla plant project.
Earnings after tax for Jan–Sep 2025 were MSEK -69.9, compared to MSEK 81.1 in the same period last year.
The Uddevalla plant reached a new milestone, with all main process equipment delivered and installed; all carbon black production capacity is fully booked for the next 5–10 years.
A partially guaranteed preferential rights issue raised MSEK 240.0 before transaction costs, with potential for an additional MSEK 90.4 from warrants.
The CEO highlighted an extended timeline for the Uddevalla plant, now targeting PAC in the second half of 2026, citing unique challenges and a focus on quality and learnings for future expansion.
Financial highlights
Q3 2025 net revenues were MSEK 1.6, down from MSEK 48.5 in Q3 2024.
Q3 2025 earnings after tax were MSEK -25.4, compared to MSEK 19.8 in Q3 2024.
Jan–Sep 2025 operating result was MSEK -69.0, down from MSEK 78.4 year-over-year.
Cash flow after investments for Jan–Sep 2025 was MSEK -145.8, compared to MSEK -91.2 last year.
Investments in fixed assets for Jan–Sep 2025 totaled MSEK 100.8, mainly in intangible assets and joint venture shares.
Outlook and guidance
The Uddevalla plant's commissioning is now expected in the second half of 2026, with all production capacity sold out for 5–10 years.
Infiniteria is advancing plans for additional recycling plants in Europe, aiming for 1 million tons of capacity by 2030.
Service offerings for new plant projects are being developed, with more details expected in Q4 2025.
Latest events from Scandinavian Enviro Systems
- Heavy losses and project delays drive uncertainty despite capital raise and strong technology interest.SES
Q4 202527 Feb 2026 - Revenue and profit fell, but funding and project milestones secure future growth.SES
Q2 202519 Aug 2025 - Strong revenue and profit growth driven by joint venture milestones and Uddevalla plant progress.SES
Q3 202413 Jun 2025 - Revenues and profits soared on JV project income as Uddevalla plant construction advances.SES
Q2 202413 Jun 2025 - Q1 2025 saw steep revenue drop but major progress on Uddevalla plant and new rights issue.SES
Q1 20256 Jun 2025 - Enviro achieved record revenues and first full-year profit, advancing its European rollout.SES
Q4 20245 Jun 2025