SeaTwirl (STW) Q3 2026 earnings summary
Event summary combining transcript, slides, and related documents.
Q3 2026 earnings summary
23 Oct, 2026Executive summary
Q3 priorities shifted to VERTI-GO commercialization and getting the 200 kW turbine into service; installation of the 1 MW S2x turbine was postponed indefinitely.
VERTI-GO passed its Basic Design milestone; the design submission was sent to the EU in late September.
A 20 MW Australian demonstration proposal and a transfer of more than SEK 38M in remaining project support strengthened the development program.
Financial highlights
Q3 net sales were SEK 0M, unchanged YoY; capitalized own work was SEK 2.3M vs SEK 0.4M, and other operating income was SEK 2.2M, mainly recognized EU grants.
Q3 operating loss was SEK 16.3M vs SEK 4.2M; net loss was SEK 14.9M vs SEK 4.2M, with development costs and S2-related impairments weighing on results.
Q3 cash flow was negative SEK 7.2M vs negative SEK 5.0M; operating cash flow was negative SEK 4.8M, and cash at quarter-end was SEK 66.4M vs SEK 30.8M.
9M net sales were SEK 0.8M; net loss was SEK 24.1M vs SEK 13.5M YoY, and EPS was negative SEK 4.02 vs negative SEK 2.26.
Outlook and guidance
The stated priority is to qualify the 200 kW turbine and secure its first installation as soon as possible, targeting initial revenue and operating experience.
VERTI-GO will continue development toward manufacturing, installation and operation of a 2 MW turbine; funding and industrial execution remain important to progress.
S2x construction and installation are deferred while resources are prioritized toward VERTI-GO; its design remains in the product portfolio.
Latest events from SeaTwirl
- Q2 2026 marked ongoing commercialization efforts, strategic partnerships, and stable liquidity.STW
Q2 2026 - Team expansion and VERTI-GO progress drive growth, with strong liquidity and new partnerships.STW
Q1 2026 - EU-funded Verti-Go project drives growth, but losses deepen amid major development investments.STW
Q4 2025 - €15M EU grant boosts 2MW turbine project as Q3 losses narrow and equity remains strong.STW
Q3 2025 - Secured key project milestones and improved financials while expanding global partnerships.STW
Q2 2025 - Q3 loss deepens as SeaTwirl prioritizes partnerships and first commercial order amid cash burn.STW
Q3 2024 - S3 turbine design finalized as SeaTwirl pivots to commercialization amid sector growth.STW
Q2 2024 - Q1 loss narrows as SeaTwirl readies major tech launch and expands global partnerships.STW
Q1 2025 - SeaTwirl deepens partnerships and streamlines operations, targeting growth in floating wind for 2025.STW
Q4 2024