19 Oct, 2026Production and operations
9M 2026 production averaged 37,100 boepd, up 44% YoY from 25,700 boepd; Q3 averaged 22,100 boepd, reflecting planned Bruce and Triton maintenance.
Triton FPSO maintenance began 27 July; an engine change-out delayed restart to around end-November. Bruce resumed production on 12 September, with output currently around 20,000 boepd net.
Current production is over 40,000 boepd before Triton resumes, including around 12,000 boepd from the acquired Southern North Sea gas portfolio; production is expected to reach around 65,000 boepd after restart.
2026 production is now expected to average just below 40,000 boepd, following the Triton maintenance extension.
Financial performance and guidance
9M revenue was $905 million, more than double $439 million in 9M 2025; Q3 revenue was $228 million versus $134 million in Q3 2025.
9M capital expenditure was $113 million versus $200 million in the same 2025 period; cash was $227 million and borrowings $300 million at 30 September, leaving net debt of $73 million.
Total liquidity was $685 million at 30 September; Q3 outgoings included a $52 million FY2025 final dividend, $27 million cash tax payment and $43 million Spirit Energy transaction payment.
2026 post-tax CFFO guidance remains $450–475 million; opex guidance is $380–400 million, excluding $65 million Lancaster spend, and capex guidance is $175–195 million.
Organic growth and portfolio
Bruce drilling is on track to start in Q3 2027; WAD5, SCE Development and SCW Development wells are planned, with first production expected within 12 months of drilling start.
Operated near-field drilling opportunities could add up to 30,000 boepd, supporting portfolio production of 50,000 boepd into the next decade.
Kyla environmental statement and field development plan have been submitted; Edradour Royal Sovereign and Spinnaker submissions are expected to follow as projects advance toward FID.
Skerryvore drilling plans are progressing for 2027; the prospect targets 135 mmboe gross unrisked resources across two reservoirs near existing infrastructure.
Partner consent was given for further Cygnus, Clipper South and Catcher infill wells; Tornado gas-processing negotiations with the Shetland Gas Plant are progressing.
Latest events from Serica Energy
- Production surged 81% and revenue more than doubled, driving a return to net cash and strong growth.SQZ
H1 2026 - Acquisition delivers a 20.7% premium, international scale, and immediate accretion.SQZ
M&A announcement - Targeting 65,000 boepd by end-2026, with short-cycle growth and a new dividend policy.SQZ
CMD 2026 - Five 2025 acquisitions doubled fields and set up major production and cash flow growth for 2026.SQZ
H2 2025 - Strong H1 cash flow and dividends offset by Triton downtime and fiscal uncertainty.SQZ
H1 2024 - Production and cash flow set to rebound in H2 2025 after Triton downtime and strong liquidity.SQZ
H1 2025 - Acquisition diversifies assets, boosts reserves, and secures a strategic UK North Sea hub.SQZ
M&A announcement - Acquisition boosts reserves, cash flow, and portfolio diversity with minimal decommissioning risk.SQZ
M&A announcement - 2026 production set to exceed 40,000 boepd, with major growth from acquisitions and asset upgrades.SQZ
Trading update