SK oceanplant (100090) Q4 2024 earnings summary
Event summary combining transcript, slides, and related documents.
Q4 2024 earnings summary
18 Nov, 2026Executive summary
FY24 revenue fell 28.4% YoY to KRW662.6bn; operating income declined 44.7% to KRW41.8bn and net income fell 70.7% to KRW16.9bn.
Operating cash flow rebounded to KRW135.4bn from an outflow of KRW138.2bn in FY23, supported by lower contract assets and working-capital movements.
Year-end backlog was KRW1,196.8bn; FY24 new orders totaled KRW530.6bn, led by offshore wind and plant projects.
Financial highlights
Consolidated revenue KRW662.6bn vs KRW925.8bn YoY; gross profit KRW72.8bn vs KRW105.0bn.
Operating income KRW41.8bn vs KRW75.6bn; net income KRW16.9bn vs KRW57.5bn; basic EPS KRW277 vs KRW1,041.
Other gains included KRW30.5bn of confirmed contract valuation profit; finance costs were KRW63.5bn, including KRW34.0bn of derivative valuation losses.
Adjusted for no items here; gross margin and operating margin are not stated in the source figures.
Outlook and guidance
Year-end order backlog reached KRW1,196.8bn, including KRW454.7bn in offshore wind and KRW735.3bn in shipbuilding/special vessels.
FY24 orders totaled KRW530.6bn: KRW482.5bn in offshore wind/plant, KRW28.5bn in repair and conversion, KRW12.9bn in steel pipe, and KRW6.7bn in shipbuilding.
The new offshore-wind yard investment runs through Dec. 2026; stated total cost is KRW1,153bn, with KRW373.5bn spent to date.
Commercial priorities include expanding offshore-wind markets in Asia, the U.S. and Europe; strengthening LNG-carrier repair and alternative-fuel conversions.
Latest events from SK oceanplant
- Higher vessel and wind sales lifted earnings, while cash flow weakened amid heavy investment.100090
Q4 2025 - Higher 9M earnings and a KRW1.315tn backlog support growth amid heavy investment and execution risks.100090
Q3 2025 - Higher H1 earnings and a KRW 1.079tn backlog, tempered by valuation losses and cash outflow.100090
Q2 2025 - H1 earnings fell YoY, but a ₩1.502tn backlog and new-yard expansion underpin growth plans.100090
Q2 2024 - Higher sales, stronger operating cash flow and a KRW 928bn backlog support major offshore-wind investment.100090
Q1 2025 - ₩1.31tn backlog cushions weaker 9M earnings as new-yard spending accelerates.100090
Q3 2024 - A ₩1,183,523m backlog supports growth plans amid weaker Q1 earnings and project-cost risks.100090
Q1 2024 - Higher Q1 profit despite lower sales; offshore wind anchors a ₩1.22tn backlog.100090
Q1 2026 - H1 profit rose despite lower revenue, with offshore wind dominating sales and backlog.100090
Q2 2026