Skeena Resources (SKE) Mining Forum Americas 2026 summary
Event summary combining transcript, slides, and related documents.
Mining Forum Americas 2026 summary
28 Sep, 2026Project overview and development progress
Eskay Creek is positioned as a rare tier 1 asset with high-grade open-pit gold and silver production, targeting 450,000 equivalent ounces annually over the first five years.
Construction is over 70% complete, with major milestones including environmental permits, a comprehensive refinancing, and an IBA agreement with the Tahltan First Nation.
CapEx estimate for redevelopment is $659 million, about 20% higher than the DFS due to inflation and stricter water management regulations.
Infrastructure is robust, with proximity to power generation, highways, and year-round access, supporting efficient operations.
Updated technical and financial metrics, including NPV and free cash flow, are expected by end of January, with production front-loaded in the initial years.
Operational and technical updates
Average grade of 5.5 g/t over the first five years ranks among the highest globally for open-pit gold mines.
Technical report update will include steeper pit slopes and integration of the SNIP underground asset, aiming for a 400,000-ounce annual run rate over 10 years.
Refinancing included a $750 million US senior secured note, reducing cost of capital from 12% to 8.5%.
Proven and probable reserves stand at 4.6 million gold equivalent ounces, with 80% in the proven category.
Ore stockpiling and pit mining are underway, with first ore expected in Q2 2027.
Construction, processing, and workforce
Mechanical installation of the process plant is over 90% complete, with only minor components remaining.
Water treatment plant phase 1 is complete, phase 2 nearing completion; permanent power tie-in expected by late November.
New employee camp, located 10 km from the mine, is designed for comfort and retention, featuring modern amenities.
Selective ore mining techniques and advanced technology are being implemented to optimize ore extraction.
Recruitment is a focus, with key management and technical staff already in place and commissioning plans being finalized.
Latest events from Skeena Resources
- Eskay Creek is on track to become a top-tier, high-grade gold and silver producer by 2027.SKE
Corporate presentation - Eskay Creek Project advances toward Q2 2027 production, facing construction and market risks.SKE
Q2 2026 - Eskay Creek advances as a high-grade, low-cost gold-silver mine with strong economics and rapid progress.SKE
Corporate presentation - Eskay Creek nears production with strong financials, advanced construction, and key permits secured.SKE
Kinvestor Mining & Energy Conference 2026 - High-grade Eskay Creek mine nears production, promising strong cash flow and growth.SKE
Mining Forum Europe 2026 - High-grade, low-cost gold-silver mine on track for 2027 production and strong cash flow.SKE
Corporate presentation - Eskay Creek is on track for Q2 2027 production, offering top-tier gold and silver output with strong economics.SKE
Corporate presentation - Eskay Creek advances toward Q2 2027 production, targeting top-tier gold-silver output.SKE
Q4 2025 - High-grade gold-silver mine nears production with strong economics and robust community support.SKE
Corporate presentation