Solaris Resources (SLS) Corporate presentation summary

Event summary combining transcript, slides, and related documents.

Logotype for Solaris Resources Inc

Corporate presentation summary

13 Apr, 2026

Investment highlights

  • Warintza project confirmed as Tier 1 with multi-decade mine life and first quartile costs, driving significant EBITDA and free cash flow generation.

  • District-scale potential with no attachment to a major, offering strategic flexibility and growth opportunities.

  • Fully funded to complete feasibility study with a US$200 million financing package secured in May 2025.

  • Social license to operate established through Impact & Benefits Agreements and government endorsements.

  • Operates in a favorable mining jurisdiction with stable fiscal regime and USD-denominated economy.

Project economics and scale

  • 312% increase in measured and indicated mineral resources compared to 2024, with reserves supporting a 22-year operation.

  • Average annual copper equivalent production of 304kt (Y1-5) and 242kt (Y1-15), with potential to extend mine life by 25-30 years.

  • First quartile all-in sustaining costs (AISC) at $0.85/lb (Y1-5) and $1.07/lb (Y1-15).

  • Post-tax NPV (8%) of $4.6bn and IRR of 26%, with a payback period of 2.6 years.

  • Annual EBITDA of $1.9bn (Y1-5) and $1.4bn (Y1-15); post-tax FCF of $1.3bn (Y1-5) and $1.0bn (Y1-15).

Resource base and production profile

  • Total reserves: 1,300 Mt at 0.41% CuEq, supporting 5,294 kt contained CuEq.

  • Measured and indicated resources: 3,746 Mt at 0.32% CuEq, totaling 11,820 kt contained CuEq.

  • Inferred resources: 2,092 Mt at 0.20% CuEq, totaling 4,276 kt contained CuEq.

  • Only 10 of the top 30 greenfield projects globally have similar scale without major company attachment.