Terrestrial Energy (IMSR) Q3 2026 earnings summary
Event summary combining transcript, slides, and related documents.
Q3 2026 earnings summary
10 Nov, 2026Executive summary
IMSR commercial operation is targeted for the mid-2030s, with fleet deployment planned in the 2030s.
Three NRC Topical Reports were submitted in 2026, meeting stated guidance; Graphite and Thermal and Electric Facility reports were among the submissions.
Selected as advanced nuclear technology supplier for Ameresco’s U.S. Army Aberdeen Proving Ground project, the third disclosed IMSR Plant project.
Financial highlights
Q3 net loss was $11.027M versus $9.279M a year earlier; 9M net loss was $30.929M versus $21.780M.
Q3 operating expenses were $13.062M, up from $8.398M YoY; R&D was $8.538M versus $4.749M, and G&A was $4.391M versus $3.362M.
Q3 cash burn was $7.1M, up $0.7M QoQ; operating activities used $7.4M in Q3 and $22.229M in 9M 2026.
R&D growth reflected fuel testing and RELLIS lease costs; G&A growth reflected stock-based compensation for new hires and increased headcount.
Q3 interest and dividend income was $1.940M, driven by higher short-term investment balances; no debt was outstanding or accruing interest in 9M 2026.
Outlook and guidance
Cash burn is expected to increase as project activity ramps, including TETRA and TEFLA; supplier and contractor work is expected to continue through Q4 and Q1 2027.
TETRA and TEFLA are planned as balance-sheet-funded engineering projects; public-sector funding for either or both could be announced in 2027.
The Natural Gas Bridge targets TEF operation before completion of the Nuclear Facility; projected time-to-power savings are 2–3 years versus a combined-cycle gas plant, subject to NRC confirmation and customer agreements.
Current cash, investments and expected capital-market access are projected to meet cash requirements for at least 12 months from the Nov. 10, 2026 issuance date, based on current operating plans.
The serviceable addressable market is projected to reach $2.3T by 2050, from $1.6T currently.
Latest events from Terrestrial Energy
- Resale registration covers 2.26 million option shares; exercise could yield ~$1.6 million.IMSR
Registration filing - A $500 million shelf accompanies conditional CVR shares as IMSR development targets mid-2030s operation.IMSR
Registration filing - LEU-powered IMSR plans pair a 10-project pipeline with recurring fuel and Core-unit revenue.IMSR
TD Nuclear Roundtable (Virtual) - Q2 net loss was $9.4M, liquidity strong at $283.4M, and addressable market rose to $2.3T.IMSR
Q2 2026 - IMSR delivers high-efficiency, modular nuclear plants for a $2.3T market by 2050.IMSR
Investor presentation - Directors elected and auditor ratified with no shareholder questions or opposition.IMSR
AGM 2026 - NRC approvals, data center deal, and $10.5M net loss define Q1 2026; liquidity remains strong.IMSR
Q1 2026 - IMSR delivers modular, efficient, and inherently safe nuclear energy for industrial and grid markets.IMSR
Investor presentation - Annual meeting to elect directors, ratify auditor, and reinforce governance and compensation policies.IMSR
Proxy filing