Tata Power Company (TATAPOWER) Q4 05/06 earnings summary

Event summary combining transcript, slides, and related documents.

Logotype for The Tata Power Company Limited

Q4 05/06 earnings summary

27 Oct, 2026

Executive summary

  • FY06 revenue from operations rose 16% to Rs. 4,562.79 crore and PAT increased 11% to Rs. 610.54 crore; operating profit fell to Rs. 835.46 crore from Rs. 952.72 crore.

  • Generation reached a record 13,746 MUs, up 3.5%; higher hydro output during a strong monsoon helped balance thermal generation and fuel costs.

  • Consolidated total income was Rs. 6,004.66 crore and profit after tax, statutory appropriations, minority interest and associate profit was Rs. 712.11 crore.

Financial highlights

  • Total income increased 13% to Rs. 4,888.40 crore; PAT grew 11% to Rs. 610.54 crore, while PBT eased to Rs. 747.45 crore from Rs. 758.79 crore.

  • Basic EPS on PAT rose 11% to Rs. 30.82; distributable profits were Rs. 575.25 crore versus Rs. 555.09 crore.

  • Other income included Rs. 131.97 crore gain on sale of the broadband business and Rs. 22.43 crore gain on sale of the Power Systems Division.

  • Fuel cost increased to Rs. 2,396.51 crore from Rs. 1,863.98 crore, mainly due to higher oil prices; power purchase cost rose to Rs. 583.20 crore from Rs. 415.70 crore.

  • Depreciation declined to Rs. 278.34 crore from Rs. 359.62 crore; interest and finance charges fell to Rs. 165.28 crore from Rs. 191.44 crore.

Outlook and guidance

  • A 250 MW Trombay coal plant was under implementation, with commissioning targeted for FY09; 100 MW diesel sets were planned as an interim supply measure, subject to approvals.

  • The 1,000 MW Maithon project, with a 74% stake, targeted commissioning in FY10; around 50% of its coal requirement was tied up.

  • A 120 MW Tata Steel captive plant was under construction at an estimated cost of Rs. 490 crore; a 1,000 MW coastal Maharashtra plant remained at an early development stage.

  • Long-term investment prospects depend on distribution reforms, fuel linkages, power offtake risk and transmission evacuation capacity; implementation pace remained uncertain.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more

Latest events from Tata Power Company