29 Oct, 2026Executive summary
FY 2012-13 revenue rose 3.12% to ₹8,269.97 crore, while PBDIT fell 38.94% and PAT fell 68.89%, reflecting domestic gas shortages, costly LNG, lower CER income and deferred recovery of power-purchase costs.
Lower gas availability cut SUGEN output and reduced overall power sales; distribution volumes grew in Ahmedabad-Surat, Bhiwandi and Agra, while Ahmedabad-Surat T&D losses improved.
UNOSUGEN’s 382.5 MW expansion entered commercial operation on 4 April 2013; DGEN and other projects faced delays, cost pressures or approval constraints.
Financial highlights
Standalone revenue from operations was ₹8,129.87 crore versus ₹7,915.61 crore; total revenue was ₹8,269.97 crore versus ₹8,019.66 crore.
Standalone PBDIT was ₹1,439.15 crore versus ₹2,357.10 crore; PBT ₹622.74 crore versus ₹1,679.25 crore; PAT ₹384.96 crore versus ₹1,237.46 crore.
Consolidated total revenue was ₹8,364.53 crore versus ₹8,063.10 crore; profit after tax and minority interest was ₹386.70 crore versus ₹1,252.59 crore.
CER income was ₹44.99 crore versus ₹324.99 crore; 0.77 million CERs were sold during the year, while CER prices fell from ~€3.77 in March 2012 to ~€0.32 in March 2013.
Outlook and guidance
DGEN’s 1,200 MW project was expected to complete in Q4 FY 2013-14, with revised project cost anticipated from additional works, foreign-exchange variation and commissioning requirements.
The 75 MW Bhud wind project was expected to commission by February 2014, subject to forest clearance.
Agra operations were expected to improve in FY 2013-14 through network upgrades, undergrounding, improved meter reading and collection efficiency.
Potential sector support included domestic gas allocation and pricing measures, coal-block reallocation, tariff revisions and debt restructuring for state distribution utilities.
Latest events from Torrent Power
- Q2 revenue rose 24% as profit grew and renewable and storage expansion advanced.TORNTPOWER
Q2 26/27 - Lower T&D losses and 56%-complete SUGEN project led the 18-month period.TORNTPOWER
Q4 05/06 - Gujarat losses fell as Bhiwandi integration and the 1,130 MW SUGEN build shaped growth.TORNTPOWER
Q4 06/07 - PAT reached Rs 211.24 crore as SUGEN’s 1,147.5 MW start-up slipped to FY09.TORNTPOWER
Q4 07/08 - PAT nearly doubled as distribution efficiency improved and SUGEN neared launch.TORNTPOWER
Q4 08/09 - SUGEN commissioning drove a sharp FY10 earnings step-up amid ambitious expansion plans.TORNTPOWER
Q4 09/10 - Higher FY11 earnings and sales, tempered by tariff, fuel-cost and project risks.TORNTPOWER
Q4 10/11 - Higher earnings and power sales, despite fuel-constrained generation, supported expansion plans.TORNTPOWER
Q4 11/12 - Revenue grew, but gas constraints and rising costs cut FY14 PAT by 75.36%.TORNTPOWER