11 Nov, 2026Executive summary
FY2024 revenue rose 55.0% to $14.8m and net profit attributable to shareholders was $0.2m, versus a $7.1m loss in FY2023; higher-margin project deliveries and impairment reversals supported the turnaround.
Performance remained constrained by elevated costs, competition, low cash and operating cash outflows; auditors highlighted material uncertainty over going concern, while issuing an unmodified opinion.
Financial highlights
Revenue increased 55.0% to $14.845m; gross profit rose to $2.527m from $0.318m and gross margin improved to 17.0% from 3.3%.
Profit before tax was $0.187m versus a $7.083m loss; net profit was $0.172m versus a $7.105m loss, and basic/diluted EPS was 0.25 cents versus a 9.57-cent loss.
Other credits reached $1.078m, including a $0.702m slow-moving inventory allowance reversal and $0.332m trade-payables write-back; financial-asset impairment reversals were $1.199m.
Finance costs rose 61.8% to $0.626m, driven by higher rates and borrowings; administrative expenses increased 20.0% to $2.861m.
Outlook and guidance
Sludge palm oil processing at the Malaysian biomass plant was targeted to begin in Q3 2024, subject to licenses and approvals, creating an additional revenue stream.
Following April 2024 approval for the plant's second upgrade phase, management was pursuing a power purchase agreement and financing; commercial electricity exports of 10MW were targeted around 2026.
Priorities include fulfilling the order book on time, winning higher-margin Singapore projects, improving supplier-chain cost control and operational efficiency, and expanding clean energy activities.
Latest events from VibroPower Corporation
- 1H profit nearly doubled, but property disposals, arbitration and bond maturity remain pivotal.BJD
Q2 2027 - Revenue rose 31.2% and net profit turned positive, despite a challenging operating outlook.BJD
H1 2023 - Delayed projects and contract provisions deepened losses as liquidity risks persisted.BJD
H2 2023 - Profit rebounded on reversals, but margins narrowed and cost pressures persist.BJD
H1 2024 - Revenue fell 41% as delayed projects and impairments drove a H1 loss.BJD
H1 2025 - Revenue fell 62.9%; recovering orders face persistent losses and going-concern uncertainty.BJD
H2 2025 - Revenue more than doubled and profitability returned, while cost and pricing pressures remain.BJD
H1 2026 - Higher project deliveries restored 9M profitability, but cash, costs and financing remain watchpoints.BJD
Q3 2026 - Revenue doubled and margins recovered, but liquidity still hinges on key milestones.BJD
Q4 2026