Vow Green Metals (VGM) H1 2024 earnings summary
Event summary combining transcript, slides, and related documents.
H1 2024 earnings summary
23 Jan, 2026Executive summary
Achieved major milestones in H1 2024, including capital raises, construction start at Hønefoss, and a long-term supply agreement with Elkem for 15,000 tons of biocarbon annually.
Early production line at Hønefoss (2,500 tons capacity) is operational, accelerating commercial deliveries and product development.
Secured NOK 344 million green loan for Hønefoss facility, with construction progressing and operations expected in H2 2025.
Strategic partnerships and investments from Vardar AS and Skagerak Energi AS strengthen financial position and project execution.
Clear ambition to reach 200,000 tons of biocarbon production by 2028 and exceed 500,000 tons by 2030.
Significant events and developments
NOK 344 million loan agreement signed with DNB and Eksfin, securing full financing for Hønefoss phase 1.
NOK 70 million equity investment from Vardar AS and Skagerak Energi AS in H1 2024.
Vardar AS became a 25% stakeholder in the Hønefoss facility through equity investment and debt conversion.
Supply agreement with Elkem ASA for up to 15,000 tons of biocarbon annually from Hønefoss.
Early production line at Hønefoss fully financed through leasing.
Capital allocation and financing
NOK 70 million capital raised in H1 2024, including NOK 50 million equity from Vardar AS and NOK 20 million from Skagerak Energi.
NOK 10 million revolving credit facility established with SpareBank 1 SR-Bank.
Leasing agreement for early production line added NOK 46.3 million to non-current assets and liabilities.
Vardar AS converted NOK 50 million loan to equity; Skagerak Energi AS invested NOK 20 million in equity.
Additional pilot equipment added to increase production capacity and develop new products.