Solid 2023 operating performance: shipments rose to 27.7M tonnes from 23.3M, while profit increased to $116.6M from $66.8M.
Potash terminal construction advanced, with major contracts in place; the project remains on schedule and is expected to begin handling potash in 2026.
Financial highlights
FY2023 revenue was $381.0M, up from $297.0M; coal loading revenue reached $360.4M versus $282.2M.
Profit before tax was $159.7M versus $91.7M; net profit was $116.6M versus $66.8M, and EPS was $1.86 versus $1.06.
Operating and administrative expenses increased to $218.7M from $195.6M, reflecting higher labour and external costs, throughput, inflation and potash-project disruption.
Operating cash flow was $189.6M versus $144.1M; cash and cash equivalents ended the year at $164.7M.
Outlook and guidance
2024 throughput is forecast at 25.5M tonnes, with an average loading charge of $13.40 per tonne, based on customer information, rail performance and site construction activity.
Potash handling is expected to commence in 2026; construction remains on schedule and is expected to finish close to the original budget despite higher-than-expected inflation.
BHP approved Jansen Stage 2, targeting production capacity of 8.5M tonnes per year, with first production expected in 2029; formal construction notification is anticipated after current-project milestones.
Latest events from Westshore Terminals Investment
- Higher coal throughput lifted earnings as potash costs rose and Berth 2 work shifted to 2027.WTE
Q3 2026 - Year-to-date profit rose 19.5% as higher coal loading revenue offset lower Q2 tonnage.WTE
Q2 2026 - Lower 2025 earnings reflect operational disruptions, but potash project and funding advance.WTE
Q4 2025 - Q1 2026 saw higher profit and revenue, strong cash flow, and progress on the potash project.WTE
Q1 2026 - Revenue up 6%, profit per share steady, potash project advances, and dividends increased.WTE
Q4 2024 - Q3 profit dropped 61% year-over-year as coal volumes fell and Berth 1 repairs continued.WTE
Q3 2025 - Q2 2025 saw lower profit and revenue, but potash project progress and cash flow remain strong.WTE
Q2 2025 - Q3 profit up year-over-year; potash project drives capex and future diversification.WTE