Wishbone Gold (WSBN) Status update summary
Event summary combining transcript, slides, and related documents.
Status update summary
7 Apr, 2026Project progress and data analysis
Seven RC holes (1,509m) and six diamond drill holes (3,298.7m) have been completed at Red Setter Gold Dome, with a final 300m diamond hole underway and drilling paused for the wet season.
Four diamond drill holes have been processed, with assays pending; approximately 1,500–1,509 RC samples and 2,178–2,200 diamond samples are in the lab or being prepared.
Analysis integrates drill data, core samples, and geophysical work to refine the geological model and plan next year's drilling.
Operations are paused for the wet season, with consolidation of geological information and resumption of drilling expected after the summer.
The Red Setter Dome breccia and surrounding Diorite remain key exploration targets.
Infrastructure and logistical improvements
Application submitted for a new ~30km access road between Nifty Copper Mine and Red Setter, with a heritage survey scheduled for early April 2026.
The new road will simplify logistics, reduce costs, and provide access to Nifty’s facilities, including accommodation, fuel, water, and airport services.
Improved access is expected to streamline future drilling programs and facilitate larger campaigns in 2026.
New access road approved, providing easier and safer entry to the site and linking to Nifty Copper Mine.
Weather conditions, including extreme heat and cyclone season, impact operational timelines, with drilling expected to resume around April.
Strategic and corporate actions
Recent share consolidation provides headroom for future fundraising and acquisitions, streamlining the capital structure.
Ongoing analysis from Expert Geophysics and core data will inform future announcements and drilling strategies.
Latest events from Wishbone Gold
- 9,000m drill campaign in 2026 targets high-grade gold-copper system with ongoing updates.WSBN
Status update8 Apr 2026 - Exploration breakthroughs and financial restructuring set the stage for 2025 growth.WSBN
H2 20247 Apr 2026 - Expanded exploration, higher loss, and strong funding position support ongoing project growth.WSBN
H2 20237 Apr 2026 - Operating losses widened and cash declined, but new funding supports continued exploration.WSBN
H1 20247 Apr 2026 - Reduced losses and strong cash position support ongoing exploration at Red Setter Dome.WSBN
H1 20257 Apr 2026