FY2026 delivered sharply higher revenue and profit on stronger metal prices and improved mining and milling volumes; safety improved, with no fatalities for a second consecutive year.
6E sales fell 2% to 598,369 oz, while final product production was broadly flat at 606,294 oz as smelter maintenance added 24,000 oz to concentrate stocks.
Financial highlights
Revenue rose 57% to US$1.299bn; gross profit reached US$437.9m, up from US$106.3m, and gross margin expanded to 34% from 13%.
PBT increased to US$387.5m from US$66.4m; PAT rose to US$276.7m from US$40.5m; basic EPS was 257 US cents versus 38 cents.
Cost of sales rose 20% to US$860.9m; higher mining and milling volumes, restored employee earnings and engineering maintenance contributed to the increase.
Net cash from operating activities was US$180.5m versus US$127.2m; free cash flow after growth capital was US$31.0m versus negative US$17.1m.
Outlook and guidance
The 45MW Phase 2A solar project is scheduled for commissioning in H1 FY2027; completion will raise installed solar capacity to 80MW.
Mupani development remains on schedule to reach 3.6Mtpa capacity by FY2029; it is intended to replace depleted Rukodzi and Ngwarati production and part of Mupfuti output.
FY2027 priorities include planned production and cost performance, SIB investment, mine replacement, solar project completion and maintaining zero-fatality performance; no numeric production guidance was stated.
Latest events from Zimplats
- 6E metal output surged 179% sequentially as costs rose and key projects advanced on schedule.ZIM
Q4 2026 TU - Final metal output plunged on smelter downtime, raising costs, while key projects advanced.ZIM
Q3 2026 TU - Production up, profit down as PGM prices fell; major projects and cost controls advanced.ZIM
H2 2024 - Revenue up 8% to US$826.6m, profit after tax US$40.5m, major projects commissioned.ZIM
H2 2025 - Net profit surged 3,376% year-over-year on strong metal prices and higher sales volumes.ZIM
H1 2026 - 6E metal output dropped 24% on higher costs, while major expansion projects advanced.ZIM
Q1 2026 TU - 6E head grade and mined volumes rose, but final product output fell amid smelter ramp-up.ZIM
Q1 2025 - Operating cash costs fell 4% year-over-year as production and capital projects progressed.ZIM
Q4 2024 - Profit rebounded to US$4.1m on higher metal prices despite lower sales volumes and revenue.ZIM