Abenójar Tungsten (ABT) investor relations material
Abenójar Tungsten Corporate presentation summary
Complete event summary combining all related documents: earnings call transcript, report, and slide presentation.Investment case and ownership
El Moto combines a strategic tungsten supply opportunity, EU location, projected low costs and project development progress; construction began in May 2026.
October 2026 London IPO raised €170M for construction; post-IPO cash was £143M, with £340M enterprise value and 67.4% institutional ownership.
Majority shareholder PMC is controlled by the García San Miguel family, whose mining experience spans Spanish operations and mine contracting.
Milestones include final construction permit and Deutsche Bank project-finance term sheet in September 2026, plus Traxys offtake agreement in October 2026.
El Moto asset and development
Underground bulk-tonnage mine planned at 1.5 Mtpa; construction is permitted, initial site works began in May 2026 and ramp development began in July.
2026 DFS cites 91.3 Mt resources at 0.38% WO3 and 0.41 g/t Au; 22.6 Mt proven and probable reserves at 0.41% WO3 and 0.40 g/t Au.
The continuous porphyry-style deposit is wolframite-dominant, with gold by-product potential; the reserve-based mine plan covers ~25% of total resources.
Mine design uses sub-level open stoping and paste backfill; the processing circuit targets 4,227 tpa WO3 and ~7,900 ozpa gold at steady state.
DFS targets first production in Q1 2029 and an 18-year reserve-only mine life; planned WO3 recovery is 72%, with 42% gold recovery.
Economics and funding
DFS base case assumes APT at $1,415/mtu and gold at $3,500/oz; post-tax NPV at 8% is €1.532B and post-tax IRR is 62%.
Base-case C1 cash cost is €188/mtu and AISC €236/mtu; C1 cash costs exclude freight and royalty expenses.
Total target funding is ~€314M, including €170M IPO proceeds, ~€120M proposed ECA project finance and €12.6M regional subsidy; Deutsche Bank signed a financing term sheet.
Existing infrastructure includes a permitted route for 45 kV grid power supplying ~14 MW and paved-road access, supporting lower upfront infrastructure needs.
)
)
)
)
)
)
)
)