Amaroq (AMRQ) investor relations material
Amaroq Corporate presentation summary
Complete event summary combining all related documents: earnings call transcript, report, and slide presentation.Operating performance and guidance
Q3 2026 production ~12.6 koz; 9M output ~21.6 koz, with Q3 head grade of 23.6 g/t from 19.3 kt milled.
Q3 revenue C$65.4M, gross profit C$45.6M and net income C$24.4M; 9M revenue C$121.6M and net income C$38.0M.
FY 2026 production guidance 25–35 koz; 9M production was 21.6 koz, with output tracking toward the mid-range.
FY guidance: cash costs US$44–47M, Nalunaq AISC US$69–73M and growth capital US$25–43M; 9M actuals were US$30.9M, US$49.9M and US$34.5M, respectively.
Q3 unaudited balance sheet: C$51.5M cash, C$54.9M net debt, C$469.3M total assets and 68% equity ratio.
Nalunaq growth plan
Nalunaq MRE reached 504 koz at 30.35 g/t Au, including 174 koz Indicated; reported increase of 10.6% versus MRE4.
Q3 drilling averaged 42.8 g/t across 27 holes; best intersection was 132.5 g/t over 0.5 m, and 30% of intersections exceeded 60 g/t.
Near-term priorities include reaching nameplate capacity, growing measured and indicated resources, and de-risking reserve definition through underground drilling.
Throughput options include ~450 tpd with an additional mill and >600 tpd with optical sorting; FY production potential is framed at 70 koz+ through expansion and continued growth.
Flotation commissioned in June 2026, with recoveries ramping toward 90–95%; underground drilling continues to test ~2 Moz exploration potential.
Multi-asset development pipeline
Three-asset plan centers on Nalunaq, Maarmorilik and Nanoq, with a phased path from one operating mine to multi-asset production.
Maarmorilik development work includes an updated MRE and PEA, with a String of Pearls concept targeting ~700 ktpa throughput using underground and open-pit mining.
Maarmorilik sampling confirmed high-grade Zn-Pb-Ag, with assays up to 62% Zn; project Terms of Reference submitted as a step toward EIA and SIA work.
Nanoq completed 4,729 m of resource drilling across 33 holes, with visible mineralisation in 88%; maiden MRE is planned for Q1 2027.
Nanoq infrastructure planning covers a beach landing, laydown area and South Bay access road; a 2027/28 bulk sample could be transported to Nalunaq for processing.
- Nalunaq’s ramp-up drove Q3 profitability, with FY output guidance held at 25–35 koz.AMRQ
Q3 2026 - Greenland mining projects advance with high-grade output, expansion, and infrastructure growth.AMRQ
Mining Forum Americas 2026 - Gold output, revenue, and profit exceeded targets, with strong ramp-up and exploration progress.AMRQ
Q2 2026 - Greenland mining operations expand with strong Q1, major exploration, and LSE main market move.AMRQ
Precious Metals & Critical Minerals Hybrid Conference - Five-year plan drives gold, zinc, and critical minerals growth with strong financial performance.AMRQ
Capital Markets Update 2026 - Strong Q1 2026 results with gold output, revenue, and exploration plans exceeding expectations.AMRQ
Q1 2026 - Strong gold production, high-grade exploration results, and robust liquidity drive growth.AMRQ
Corporate presentation - High-grade gold and copper confirmed at Nanoq, supporting major expansion and resource drilling in 2026.AMRQ
Status Update - First gold pour, 51% resource boost, and $124M+ raised highlight a pivotal 2024.AMRQ
Q4 2024
)
)
)
)
)
)
)
)