Diatreme Resources Q3 2026 TU earnings summary
Complete event summary combining all related documents: earnings call transcript, report, and slide presentation.Executive summary
Post-quarter PFS outlined a 25-year Northern Silica Project (NSP), with a 3 Mtpa base case and a potential 5 Mtpa expansion from Year 3.
The Cape Flattery Silica Project sale to the DRX/Sibelco joint venture generated total funding of ~$7.4 million; the resulting joint venture interest is 73.2%.
September-quarter-end cash was $1.919 million, with a further $6.9 million held in the silica joint venture; combined cash was $8.8 million.
Financial highlights
Half-year net loss to 30 June 2026 was $3.025 million, versus a $0.728 million loss in 2025.
Q3 net operating cash outflow was $684,000; investing outflow was $114,000 and financing outflow was $17,000.
Nine-month net operating cash outflow was $2.041 million; cash and cash equivalents closed at $1.919 million.
Outlook and guidance
PFS Phase 1 base case: 3 Mtpa over 25 years, with pre-tax NPV of $1.290 billion, pre-tax IRR of 36%, and four-year payback.
Potential Phase 2 from Year 3 lifts production to 5 Mtpa; PFS estimates pre-tax NPV of $2.419 billion and pre-tax IRR of 46%, with $38.5 million additional capex.
Definitive Feasibility Study (DFS) completion is targeted for Q2/Q3 CY2028, with Final Investment Decision (FID) targeted for Q3 CY2028.
December-quarter priorities include NSP permitting, port-access negotiations and Traditional Owner agreement discussions; Cyclone options include sale, joint venture or asset spin-out.
- Net loss increased to $3.0 million amid higher costs and asset divestment, with improved cash from JV funding.DRX
H1 2026 - High-purity silica project advances toward Q3 2026 PFS, backed by Sibelco and strong demand.DRX
Noosa Mining Conference 2026 - Resource upgrades, asset sale, and new JV funding drive project advancement and financial strength.DRX
Q2 2026 TU - Silica and zircon projects advanced, asset sale boosts funding, net loss widens year-over-year.DRX
Q1 2026 TU - 278% resource upgrade and regulatory progress at NSP, with net loss of $744,955 in 2025.DRX
H2 2025 - Metallica Minerals acquisition completed, silica resources expanded, and regulatory progress achieved.DRX
H2 2024 - Clermont sale, regulatory milestones, and improved Cyclone recoveries strengthen financials.DRX
Q4 2025 TU - High-purity silica sand projects advance toward 2027 production and major approvals.DRX
Noosa Mining Investor Conference - High-purity silica sand projects in Queensland advance toward 2027 production for solar demand.DRX
Noosa Mining Investor Conference
)
)
)
)
)
)
)
)