Complete event summary combining all related documents: earnings call transcript, report, and slide presentation.Construction and commissioning
Construction 65% complete at 30 September 2026; capital expenditure $1,237m against a total capital estimate of $1.7–1.8bn. All major equipment delivered and engineering 100% complete.
SMPEI works advancing, with pipe racks, large tanks and main SX circuit buildings progressing; commissioning of completed packages underway and switchrooms energized.
Construction completion and a two-year ramp-up are planned; commissioning priorities include operator training, stable processes and mineral commissioning with Eneabba feedstock.
Refinery design and capacity
Designed for flexible feed sources and rare earth oxide output; the process uses conventional sulfuric cracking, leaching and nitrate-based separation.
Nameplate concentrate capacity is 55ktpa; total rare earth oxide capacity is 23,000tpa, including 5,500tpa NdPr oxide and 750tpa DyTb oxide.
Light rare earth circuit capacity is 17ktpa, with short-term capacities fixed; additional separation capacity, including for yttrium oxide, could be considered post-commissioning.
Design features include progressive neutralisation for purification, seven main separation stages and permanent, lined waste storage in an ex-mine void.
Feedstock and production options
Supply sources include the Eneabba stockpile, Balranald and third-party projects including Lindian Resources’ Kangankunde, VHM’s Goschen and Northern Minerals’ Browns Range.
Illustrative blends range from a light rare earth focus using Eneabba and Balranald to a heavy rare earth focus incorporating Wimmera, Northern Minerals and VHM feedstocks.
Illustrative outputs span 3,600–4,300tpa NdPr, ~180–1,000tpa DyTb and 350–5,000tpa HRE plus yttrium contained in carbonate, depending on feed blend.
- Q3 zircon pricing strengthened as Balranald ramp-up and Eneabba construction progressed.ILU
Q3 2026 TU - Cash flow surged and debt fell as key projects advanced, despite lower H1 revenue.ILU
H1 2026 - Lower H1 2026 production offset by strong cash flow and rare earths milestones.ILU
Q2 2026 TU - AGM confirmed strategic progress on rare earths, disciplined finances, and board transitions.ILU
AGM 2025 - Integrated rare earths refinery set for 2027, fully funded and backed by long-term supply deals.ILU
Investor presentation - Revenue and profit fell, but cost cuts and rare earths progress support the 2026 outlook.ILU
H2 2025 - Net profit dropped 31% as revenue and prices fell, but key projects and cost controls advanced.ILU
H1 2025 - Revenue and profit fell, but stable pricing and project progress support future growth.ILU
H1 2024 - Revenue and profit fell, but margins held and major projects are fully funded.ILU
H2 2024
Next Iluka Resources earnings date
Next Iluka Resources earnings date
AI chat
Ask anything. Verify everything.
Ask across every event and document from public companies. Each answer links back to the exact line in the transcript, slide or filing it came from.Learn moreFind what matters
AI across all first-party IR material. Live calls, transcripts, slides, filings.)
Trust every finding
50m+ first-party documents. Every output traceable to its source.Automations
Zero in on what matters
Define the prompt once. It runs the moment a company publishes or on a schedule you set. Outputs map to the exact signals you choose.Learn more)
Event-triggered research
Runs when a company publishes new material. Trigger on the first published document for the earliest possible run, or wait for a specific one.)
Scheduled research
Runs on a recurring cadence you set. Daily, weekly, monthly, or quarterly, for aggregate reads across a period rather than a single event.Live audio & transcripts
Be first
Join any earnings call live in one click, with no manual registration. Follow the transcript as it happens and jump straight to the moments that matter.Learn more)
Live earnings calls
Join any call in one click. The audio keeps playing while you work elsewhere in Quartr.)
Live transcripts
Speaker-by-speaker, in real time. Searchable across every live and historical call.Quartr MCP connects your AI environment to 17K+ public companies
Quartr's AI stands out because it only pulls clean, first-party data from public companies. In investing, that's everything.
Jamie Ross
Investment Manager, GAM Investments
Research that used to take hours now takes seconds with Quartr Pro. Tracking shifts in tone or extracting tables, it's as simple as typing a query.
Tom O'Hara
Investment Director
Before Quartr we spent hours manually compiling insights through the peer earnings cycle. Now, these tasks are done faster, with greater precision.
Gregg Lampf
VP of Investor Relations
Being able to ask specific questions across years of transcripts and reports and instantly get verified answers is a game-changer.
Pontus Dackmo
CEO & Investment Manager
)
)
)
)