Meeka Metals (MEK) investor relations material
Meeka Metals Q1 2027 TU earnings summary
Complete event summary combining all related documents: earnings call transcript, report, and slide presentation.Executive summary
Produced 7,237oz of gold in the Sep-26 quarter, up from 6,424oz in Jun-26, as underground output ramped up and the processing plant reached its 600ktpa annualised target.
Shifted focus from open-pit mining to higher-grade underground operations; the Fairway decline at Turnberry is under development, with first ore expected in Jan-27.
Cash closed at $51.2M after a placement and $8.5M net mine cash flow; operations remain unhedged and have no debt other than mining equipment finance.
Financial highlights
Gold sales of 7,279oz generated $44.1M revenue at an average realised price of $6,063/oz.
All-in sustaining cost (AISC) was $4,147/oz; cash operating cost was $3,545/oz, including a favorable ore inventory adjustment of $357/oz.
Mine operating cash flow was $13.5M and net mine cash flow was $8.5M after $4.9M growth capital; depreciation and amortisation was $9.5M.
Appendix 5B reported $1.548M net cash from operating activities and $17.411M net investing cash outflow; financing generated $29.085M net cash.
Outlook and guidance
First ore from the Fairway decline is expected in Jan-27, adding a second high-grade underground ore source and reducing reliance on a single mining area.
Stage 1 of the two-stage tailings storage facility is expected to be commissioned in the Dec-26 quarter; the facility is designed for 10 years of capacity at 600ktpa.
The Steinert multi-sensor ore sorter was installed in early Oct-26, with commissioning commencing mid-October.
Underground drilling from Fairway platforms is planned to test mineralisation below the current Ore Reserve and support potential resource-to-reserve conversion and mine-life extension.
- Production rose to 7,237oz as the operation shifted toward underground growth.MEK
Trading update - Underground mining ramp-up and Mt Holland acquisition drive growth, profitability, and resource expansion.MEK
Mining Forum Americas 2026 - First full year of gold production delivered $160.8M revenue and $51.3M net profit.MEK
H2 2026 - Transition to underground mining and exploration drive improved grades, production, and growth.MEK
Noosa Mining Conference 2026 - Transition to higher-grade underground ore is set to drive improved production and cash flow.MEK
Q4 2026 TU - Strong cash flow and plant upgrades position for higher gold output despite recent production dip.MEK
Q3 2026 TU - Murchison Gold Project fully funded and approved, targeting first production in mid-2025.MEK
H2 2024 - First gold production achieved, strong capital raising, and major ramp-up in mine development.MEK
H2 2025 - Delivered $31M net profit and strong cash flow following first gold production at Murchison.MEK
H1 2026
)
)
)
)
)
)
)
)