Complete event summary combining all related documents: earnings call transcript, report, and slide presentation.Executive summary
Crixás Gold Tailings Project permitting advanced: the environmental impact statement and supporting reports were resubmitted to SEMAD for review; production potential remains conditional on permits and further technical work.
Quarter-end cash was $11.73m, supporting Crixás evaluation and assessment of acquisition opportunities; divestment and joint-venture options for non-core assets remain under review.
Financial highlights
Cash and cash equivalents were $11.732m at 30 September 2026, down $248k during the quarter; operating cash outflow was $248k, with $146k interest received and a $4k adverse exchange-rate effect.
Exploration and evaluation payments were $202k; staff and board remuneration was $52k and administration and corporate costs were $140k.
Related-party payments totalled $134k: $99k for director fees and $35k for accounting and company secretarial services.
Outlook and guidance
Subject to permit re-issue and SEMAD verification, the Crixás project is to be evaluated for near-term production potential; the concept remains subject to technical evaluation and approvals.
Planned work includes resource drilling to support a JORC-compliant estimate, metallurgical evaluation focused on gravity and potentially flotation, and work toward FID as soon as practicable.
Preliminary cost estimate for the work program toward FID is less than A$1m; the estimate is preliminary and subject to change.
- Net loss of $10.63 million, strong liquidity, and key project advances in Brazil, Bulgaria, and Australia.RDN
H2 2026 - Permitting advances at Crixás and new Vuzel targets drive growth, with $11.98m cash on hand.RDN
Q4 2026 TU - Crixás Gold Tailings Project advances toward FID as cash reserves remain robust at $12.33m.RDN
Q3 2026 TU - Net loss narrowed to $3.66 million as exploration advanced and cash reserves rose to $5.71 million.RDN
H2 2024 - Loss narrowed, exploration advanced in Europe, and a new Brazilian gold project was acquired.RDN
H1 2026 - Net loss widened to $6.98M as exploration ramped up, funded by a $10M capital raise.RDN
H2 2025 - Net loss widened to $3.99M as exploration ramped up and $14.7M was raised for drilling.RDN
H1 2025 - Strong gold and silver results at Vuzel, robust cash, and 100% Mt Sholl ownership retained.RDN
Q1 2026 TU - Vuzel drilling success boosts ownership to 75% as cash reserves remain robust at $14.04m.RDN