Tivan (TVN) investor relations material
Tivan Investor presentation summary
Complete event summary combining all related documents: earnings call transcript, report, and slide presentation.Speewah development
Speewah is planned as an integrated Western Australian mine and processing operation, with construction targeted for 2027 and first production targeted for 2028.
The March 2026 Feasibility Study targets annual life-of-mine averages of 149,000 tonnes of acidspar and 15,500 tonnes of metspar, from 1.15 Mtpa ore processing over an initial 10-year mine life.
The Definitive Feasibility Study is progressing toward completion in 2026; development work includes mine planning, project finance, environmental approvals, Traditional Owner agreements and product qualification.
The Feasibility Study production case uses the 2024 resource; the 2026 resource update and completed project drilling are supporting mine planning and a maiden Ore Reserve.
Speewah resource and product
The 2026 Mineral Resource Estimate is 43.2 Mt at 8.3% CaF2, containing 3.588 Mt CaF2; the high-grade component is 9.6 Mt at 20.6% CaF2.
The resource update increased tonnage by 16% and contained CaF2 by 6%; 37,000 m of project development drilling is complete, with a further resource update targeted for November 2026.
The completed mini pilot produced approximately 195 kg of acidspar at a weighted-average grade of 98.6% CaF2, above the 97% benchmark; samples were delivered to potential end users for evaluation.
Acidspar samples demonstrated low arsenic, sulphides and phosphorus; potential end users appraised samples supplied through Sumitomo.
Partnership and financing
The binding joint venture brings together Sumitomo Corporation and JOGMEC, through Japan Fluorite Corporation, for Speewah development, financing and operation.
JFC investment is stage-gated across the Feasibility Study, Definitive Feasibility Study and Final Investment Decision, with each equity tranche funding the next development phase.
The offtake term sheet covers up to 100% of life-of-mine production, including an 80% take-or-pay commitment; Sumitomo has worked on offtake strategy and product specification since Q2 2024.
Export Finance Australia and the Northern Australia Infrastructure Facility are identified in the project financing pathway; the presentation describes a planned pathway for conditional debt finance.
- High-grade exploration results and project milestones advanced against $19.925m quarter-end cash.TVN
Q1 2027 TU - Speewah nears FID as drilling, resource upgrades, and JV partnerships drive momentum.TVN
Investor update - Significant project progress, resource upgrades, and capital inflows drive growth despite higher loss.TVN
H2 2026 - JV funding, robust project economics, and strong cash position drive project advancement.TVN
Q4 2026 TU - Speewah and Molyhil advanced with strong economics, key partnerships, and expanded operations.TVN
Investor update - Speewah Fluorite Project advances with resource upgrade, funding, and strategic recognition.TVN
Q3 2026 TU - Speewah Fluorite Project advanced with Sumitomo alliance, robust PFS, and major capital raisings.TVN
H2 2024 - Speewah project advanced, net loss narrowed, and capital raised for critical minerals growth.TVN
H2 2025 - Board and shareholders backed growth plans, with high turnout and all resolutions supported.TVN
AGM 2025
Next Tivan earnings date
Next Tivan earnings date
AI chat
Ask anything. Verify everything.
Ask across every event and document from public companies. Each answer links back to the exact line in the transcript, slide or filing it came from.Learn moreFind what matters
AI across all first-party IR material. Live calls, transcripts, slides, filings.)
Trust every finding
50m+ first-party documents. Every output traceable to its source.Automations
Zero in on what matters
Define the prompt once. It runs the moment a company publishes or on a schedule you set. Outputs map to the exact signals you choose.Learn more)
Event-triggered research
Runs when a company publishes new material. Trigger on the first published document for the earliest possible run, or wait for a specific one.)
Scheduled research
Runs on a recurring cadence you set. Daily, weekly, monthly, or quarterly, for aggregate reads across a period rather than a single event.Live audio & transcripts
Be first
Join any earnings call live in one click, with no manual registration. Follow the transcript as it happens and jump straight to the moments that matter.Learn more)
Live earnings calls
Join any call in one click. The audio keeps playing while you work elsewhere in Quartr.)
Live transcripts
Speaker-by-speaker, in real time. Searchable across every live and historical call.Quartr MCP connects your AI environment to 17K+ public companies
Quartr's AI stands out because it only pulls clean, first-party data from public companies. In investing, that's everything.
Jamie Ross
Investment Manager, GAM Investments
Research that used to take hours now takes seconds with Quartr Pro. Tracking shifts in tone or extracting tables, it's as simple as typing a query.
Tom O'Hara
Investment Director
Before Quartr we spent hours manually compiling insights through the peer earnings cycle. Now, these tasks are done faster, with greater precision.
Gregg Lampf
VP of Investor Relations
Being able to ask specific questions across years of transcripts and reports and instantly get verified answers is a game-changer.
Pontus Dackmo
CEO & Investment Manager
)
)
)
)