Alligator Energy (AGE) Q3 2026 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q3 2026 TU earnings summary
23 Apr, 2026Executive summary
Transitioned from project construction to trial uranium extraction at Samphire, with pilot plant commissioning completed and uranium extraction initiated via Field Recovery Trial (FRT).
Early FRT results post-quarter end show recovery performance and operating parameters meeting or exceeding expectations.
Bankable Feasibility Study (BFS) commenced, integrating real operational data from FRT to de-risk project development.
Leadership structure strengthened, including appointment of CEO as Managing Director and planned Board transitions.
Financial highlights
Cash balance at 31 March 2026 was A$13.3 million, down from A$20.6 million in the previous quarter.
Net cash used in operating activities for the quarter was A$1.45 million; net cash used in investing activities was A$5.79 million.
Exploration and evaluation expenditure for the quarter totaled A$5.7 million, reflecting increased activity from FRT operations.
Estimated quarters of funding available is 1.87, with additional proceeds expected from asset sales and R&D tax refund.
Outlook and guidance
BFS completion targeted for first half of 2027, aligning with development and permitting timelines.
Updated Mineral Resource Estimate for Samphire, including Plumbush, expected in June 2026 quarter.
Aggressive drilling campaign at Samphire planned to support resource extension and project economics.
FRT operations to transition to next wellfield after April 2026, with ongoing data generation and optimisation.
Latest events from Alligator Energy
- Samphire resource expanded, Big Lake discovery made, and $17.25M raised amid strong uranium market.AGE
H2 202531 Mar 2026 - Improved project economics, new uranium discovery, and strong cash position drive future growth.AGE
H2 202431 Mar 2026 - Nuclear energy demand is surging, but uranium supply remains tight, creating major investment opportunities.AGE
JMM & Tribeca Nuclear Energy Forum 202629 Mar 2026 - Samphire pilot plant completed, NT assets divested, net loss rises to $4.96M on impairment.AGE
H1 202622 Mar 2026 - Samphire Uranium Project advances toward production with robust economics and major exploration upside.AGE
Investor presentation16 Feb 2026 - Samphire Uranium Project advances with field trials, resource growth, and strong market demand.AGE
Noosa Mining Investor Conference3 Feb 2026 - Resolutions for share placement and options passed; Sandfire project moves to field trials.AGE
EGM 202523 Nov 2025 - Samphire Uranium Project advances toward trial production with robust financials and growth plans.AGE
AGM 2025 Presentation20 Nov 2025 - Field trials and feasibility studies progress, with robust funding and major exploration underway.AGE
Noosa Mining Investor Conference16 Nov 2025