Blackwater Mine is one of Canada's largest gold mines, now in commercial production with 8 million ounces of gold reserves and reported AISC of US$828/oz, among the lowest globally.
Over $200 million invested since 2020 with no equity dilution during construction; board and management own 39% fully diluted.
Located in British Columbia, a Tier 1 jurisdiction with strong infrastructure, stable regulatory environment, and significant local and Indigenous support.
First gold poured in January 2025, commercial production declared in May 2025, and plant operating above design capacity.
Operational and financial performance
Q3 2025 saw gold production of 60,985 oz, up from 50,623 oz in Q2, with mill averaging 101% of design capacity and gold recoveries at 87% in August and September.
Q3 2025 AISC margin was US$2,374/oz (72% of cash revenue), with cash costs at US$661/oz and AISC at US$840/oz.
Net income for Q3 2025 was $110.9M, with adjusted EBITDA of $211.4M and strong cash flow from operations.
Paid down $67M of debt in Q3 2025, refinanced project debt into a $700M revolving credit facility, and ended Q3 with $317M in liquidity.
Growth initiatives and expansion plans
Phase 1A construction began in September 2025, targeting a 33% increase in plant throughput to 8Mtpa by Q4 2026, funded through operating cash flow with a payback of less than 6 months.
Phase 2 expansion is being optimized and accelerated, with major mill orders placed and an investment decision expected by end of 2025; construction to start Q2 2026.
Resource expansion and regional exploration underway, with a $5M drill program launched in October 2025 across a 1,490 km² land package.
Latest events from Artemis Gold
- Q3 2025 saw record gold output, high margins, and robust cash flow amid rising cost guidance.ARTG
Q3 202519 Mar 2026 - Record gold output, strong margins, and a new dividend policy drive robust growth outlook.ARTG
Q4 202519 Feb 2026 - Blackwater mine targets over 500,000 oz gold annually with industry-low costs and strong growth.ARTG
Corporate presentation19 Feb 2026 - Phase 2 expansion targets 21 Mtpa and over 500,000 oz annual gold output by 2028.ARTG