Artemis Gold (ARTG) Status Update summary
Event summary combining transcript, slides, and related documents.
Status Update summary
17 Dec, 2025EP2 Expansion Approval and Project Scope
Board approved a CAD 1.44 billion investment for Expanded Phase 2 (EP2), increasing throughput to 21 million tonnes per annum by end of 2028, with potential for further increases post-commissioning.
EP2 is a standalone facility adjacent to Phase 1A, enabling parallel construction and operations with minimal disruption and de-risking.
The expansion will be funded primarily from operating cash flow, with no anticipated equity dilution and support from a strong balance sheet and undrawn RCF of $242M.
Mill recoveries are expected to average 93% post-expansion, and mine life is projected through at least 2043, with further extension potential.
EP2 will generate over 1,500 direct construction jobs at peak and increase long-term employment to around 1,200, with significant economic and community benefits, including a 25% Indigenous employment target.
Production, Cost, and Operational Guidance
Gold production is expected to exceed 500,000 ounces per year for the first 10 years post-expansion, making the site one of Canada's largest gold mines.
All-in Sustaining Costs (AISC) are projected at $1,000–$1,100 per ounce over the next decade, with margins of about 75% at current gold prices and lowest quartile cost structure.
Annual gold production guidance: 190,000–210,000 oz in 2025, 275,000–425,000 oz during 2026–2028, and 500,000–525,000 oz from 2029–2038.
Cost structure benefits from economies of scale, low strip ratio, simple metallurgy, and access to low-cost hydroelectric power.
Power requirements for EP2 will be met by an additional 50 MW from BC Hydro at standard industrial rates, with infrastructure already in place and confirmation expected in early 2026.
Project Execution, Timeline, and Risk Management
Orders for long-lead items, including primary grinding mills, have been placed, with early works starting in Q1 2026 and major construction in Q3 2026.
Phase 1A expansion to 8 Mtpa is on track for completion by end of 2026, with most procurement packages committed.
Operational flexibility is enhanced by two independent plants, allowing for blending, campaigning, and risk mitigation.
Permitting and power supply confirmations are expected in early 2026, with no major infrastructure upgrades required and alignment with environmental certificates.
Expansion and operational plans are subject to risks including permitting, commodity prices, supply chain, and technical factors.
Latest events from Artemis Gold
- Q3 2025 saw record gold output, high margins, and robust cash flow amid rising cost guidance.ARTG
Q3 202519 Mar 2026 - Record gold output, strong margins, and a new dividend policy drive robust growth outlook.ARTG
Q4 202519 Feb 2026 - Blackwater mine targets over 500,000 oz gold annually with industry-low costs and strong growth.ARTG
Corporate presentation19 Feb 2026 - Blackwater Mine delivers strong cash flow, low costs, and significant growth potential.ARTG
Corporate Presentation16 Dec 2025 - Q2 2025 delivered strong production, low costs, and a $700M facility to fund future growth.ARTG
Q2 202523 Nov 2025