OCCP holds a 130.1 Mt JORC Coal Reserve and 97.9 Mt Marketable Reserve, supporting a forecast 31-year mine life; 100% project interest.
Development advanced through CHPP site establishment and Ovoot Bond placements; key statutory approvals are in place, with remaining approvals and agreements progressing.
Financial highlights
Quarter-end cash and cash equivalents were US$2.067 million, compared with US$2.503 million at the prior quarter end.
Quarterly operating cash outflow was US$774,000; investing outflow was US$9.391 million, including US$9.022 million for property, plant and equipment.
Financing cash inflow was US$9.716 million, comprising US$10.056 million of borrowings less US$340,000 of financing transaction costs.
Director fees of US$156,000 were paid during the Quarter.
Outlook and guidance
Updated model forecasts Phase 1 pre-production infrastructure capex of ~US$61.2 million from 2026 to first scheduled production; excludes ~US$24.6 million working capital and capex incurred to 31 Dec 2025.
Economic evaluation: post-tax NPV10 US$1,483.3 million and post-tax real IRR ~60%, based on assumed long-term coking coal price of US$230/t DDP Erlian, China.
Model assumes KK raises ~US$126 million through OTC bonds and defers US$42 million of CCTEG-IEC payments until after commissioning; financing assumptions do not assure funds will be raised on schedule or terms.
Latest events from Aspire Mining
- Ovoot targets 5 Mtpa of fat coal as northern China faces an 18.1 Mt supply gap.AKM
Investor presentation - Loss narrowed, cash declined, and bond funding began, but going concern risk persists.AKM
H1 2026 - Reported $12.8m net loss, signed major EPC contract, and requires further funding for project build.AKM
H2 2025 - OCCP advanced to development with strong approvals, $6.7M profit, and funding focus for 2025.AKM
H2 2024 - H1 2025 loss driven by FX impacts; Ovoot project advances, but funding for full build remains needed.AKM
H1 2025 - Premium coking coal project near China, fully permitted and advancing rapidly toward production.AKM
Corporate Presentation - Ovoot offers robust economics, rapid development, and strong market positioning for premium coking coal.AKM
Investor Presentation - Half-year net profit rose to $2.74M as Ovoot Project development advanced.AKM
H1 2024 - AGM advanced Ovoot Project with permits, strong economics, and 2026 production target.AKM
AGM 2025