Atome (ATOM) H2 2023 earnings summary
Event summary combining transcript, slides, and related documents.
H2 2023 earnings summary
8 Apr, 2026Executive summary
Aiming to develop the world's largest green fertilizer facility by 2027, with the 145 MW Villeta project in Paraguay and additional flagship projects in Costa Rica and the 300 MW Iguazu/Yguazu project, targeting significant decarbonization of the fertilizer sector.
Villeta project targets 264,000 tons/year of calcium ammonium nitrate, with income from day one of production and construction expected to start post-FID by end of 2024.
Completed FEED for Villeta, selected Casale as EPC contractor, acquired land, and secured environmental and operational licenses.
Management and board have deep industry experience, strong local presence, and backing from major shareholders including Schroders, Baker Hughes, and Trafigura.
Focused on decarbonizing a sector responsible for 5% of global emissions.
Financial highlights
Ended 2023 with a US$6.8 million loss, with US$4.8 million capitalized as project development costs for Villeta.
Raised US$5.1 million in 2023 and an additional US$2.5 million in early 2024, with management and major shareholders participating.
Market capitalization as of 25 June: US$28.5 million; issued shares: 44,923,186; share price: 56p.
Outlook and guidance
Targeting FID and start of construction for Villeta by end of 2024, with commercial production expected in 2027.
Offtake agreement for Villeta expected in early Q3 2024; project funding and EPC contract to be finalized in H2 2024.
300 MW Iguazu/Yguazu and Costa Rica projects targeting PPAs by end of 2024.
Expects rapid commercialization and value creation post-FID, aiming to replicate the business model across new projects.
Latest events from Atome
- Villeta targets 260,000 t/y green fertilizer, $70M EBITDA, and H1 2025 financial close.ATOM
Investor update1 Apr 2026 - Villeta secures full offtake, targets 2027 production, and accelerates green fertilizer expansion.ATOM
Investor update31 Mar 2026 - Villeta Project nears FID, securing Yara offtake and major finance for low-carbon fertiliser growth.ATOM
Investor presentation31 Mar 2026 - Advanced Villeta project financing and execution, with loss of $7.3M and FID targeted for H2 2025.ATOM
H2 202431 Mar 2026 - Villeta project advances toward FID as H1 2024 loss narrows and financing interest surges.ATOM
H1 202431 Mar 2026 - Villeta project secured key financing and advanced toward construction, with losses narrowing per share.ATOM
H1 202531 Mar 2026