Atome (ATOM) H2 2024 earnings summary
Event summary combining transcript, slides, and related documents.
H2 2024 earnings summary
31 Mar, 2026Executive summary
Achieved major milestones in 2024, including completion of FEED for the Villeta Project, securing a 30-year free trade zone, and signing long-term offtake with Yara International.
Entered advanced financing and equity discussions for the $600+ million Villeta project, with Hy24 as anchor investor and a $465 million EPC contract signed.
Launched ATOME POWER division to diversify income streams and signed a framework agreement with Costa Rica's national power company.
Focused on closing Villeta financing and construction start in H2 2025, with production targeted for end of 2028.
Financial highlights
Total comprehensive loss for 2024 was $7.3 million, compared to $6.6 million in 2023, reflecting ongoing development investment.
Administrative expenses decreased to $6.95 million from $7.27 million year-over-year.
Cash and cash equivalents at year-end were $0.2 million, down from $0.6 million in 2023.
Raised $6.3 million in 2024 through share placings, with $3.7 million received in cash and $3.0 million settled in kind.
Intangible assets increased to $6.0 million, mainly due to capitalised FEED costs for Villeta.
Outlook and guidance
Final Investment Decision (FID) for Villeta targeted for H2 2025, with construction to follow.
Cash generative production expected in 2028, with Villeta as the flagship project.
Further funding required to reach project financing and operational milestones.
Latest events from Atome
- Villeta green fertilizer project nears FID with funding, permits, and 2027 output target.ATOM
H2 20238 Apr 2026 - Villeta targets 260,000 t/y green fertilizer, $70M EBITDA, and H1 2025 financial close.ATOM
Investor update1 Apr 2026 - Villeta secures full offtake, targets 2027 production, and accelerates green fertilizer expansion.ATOM
Investor update31 Mar 2026 - Villeta Project nears FID, securing Yara offtake and major finance for low-carbon fertiliser growth.ATOM
Investor presentation31 Mar 2026 - Villeta project advances toward FID as H1 2024 loss narrows and financing interest surges.ATOM
H1 202431 Mar 2026 - Villeta project secured key financing and advanced toward construction, with losses narrowing per share.ATOM
H1 202531 Mar 2026