Investor presentation
Logotype for Aura Energy Limited

Aura Energy (AEE) Investor presentation summary

Event summary combining transcript, slides, and related documents.

Logotype for Aura Energy Limited

Investor presentation summary

18 Oct, 2026

Tiris project and economics

  • 2026 BFS targets first ore by end-2028 after about two years of construction; 46.1 Mlb saleable U3O8 over a 26-year mine life, averaging 1.8 Mlb/year.

  • At US$90/lb, post-tax NPV8 is US$500.3M on a 100% ungeared basis, with 28% IRR and 3.2-year payback from first production.

  • Development capital is US$349.8M; C1 cash cost is US$32.53/lb and AISC US$41.25/lb. Life-of-mine capital totals US$573.3M, including closure.

  • Ore Reserve increased 11% to 37.3 Mlb; the production schedule uses 67.1% Ore Reserves and 32.9% Inferred Resources by ore tonnes.

  • Inferred material is under 12% of ore mined in the first five years and under 25% in the first ten; the project plans infill drilling ahead of later mining, with no certainty of conversion.

Mine and processing design

  • Shallow, free-dig ore typically sits 6–8 m below surface; no blasting, crushing or grinding is required, with a 1.00:1 waste-to-ore ratio.

  • Screening sends 91.9% of uranium into about 12% of feed mass, producing leach feed averaging 1,697 ppm U3O8; overall recovery from run-of-mine ore to final product is 83.7%.

  • A central leach plant is supplied by two relocatable beneficiation plants; the 550 ktpa leach circuit is the operation’s throughput constraint.

  • The BFS assumes an 85% renewable solar-and-battery microgrid, 13 MW peak load and US$0.15/kWh power price; a power purchase agreement is expected in Q1 2027.

Funding and execution

  • The US$400M funding plan assumes US$220M debt and US$180M equity or quasi-equity; discussions with the US DFC cover US$150–170M of senior debt.

  • Funding is not secured and no lender or investor has committed; the final funding mix remains undetermined, and equity or quasi-equity may substantially dilute shareholders.

  • A pilot plant using real ore is scheduled to run from November 2026, testing the full flowsheet; the board’s FID decision is targeted for December 2026.

  • Principal Mauritanian approvals are granted; remaining routine water, power, transport and export permits are expected through 2027.

  • Construction is planned to start in Q1 2027, with first ore by end-2028 and nameplate production targeted for 2030.

Partial view of Summaries dataset, powered by Quartr API