Aura Energy (AEE) Investor presentation summary
Event summary combining transcript, slides, and related documents.
Investor presentation summary
18 Oct, 2026Tiris project and economics
2026 BFS targets first ore by end-2028 after about two years of construction; 46.1 Mlb saleable U3O8 over a 26-year mine life, averaging 1.8 Mlb/year.
At US$90/lb, post-tax NPV8 is US$500.3M on a 100% ungeared basis, with 28% IRR and 3.2-year payback from first production.
Development capital is US$349.8M; C1 cash cost is US$32.53/lb and AISC US$41.25/lb. Life-of-mine capital totals US$573.3M, including closure.
Ore Reserve increased 11% to 37.3 Mlb; the production schedule uses 67.1% Ore Reserves and 32.9% Inferred Resources by ore tonnes.
Inferred material is under 12% of ore mined in the first five years and under 25% in the first ten; the project plans infill drilling ahead of later mining, with no certainty of conversion.
Mine and processing design
Shallow, free-dig ore typically sits 6–8 m below surface; no blasting, crushing or grinding is required, with a 1.00:1 waste-to-ore ratio.
Screening sends 91.9% of uranium into about 12% of feed mass, producing leach feed averaging 1,697 ppm U3O8; overall recovery from run-of-mine ore to final product is 83.7%.
A central leach plant is supplied by two relocatable beneficiation plants; the 550 ktpa leach circuit is the operation’s throughput constraint.
The BFS assumes an 85% renewable solar-and-battery microgrid, 13 MW peak load and US$0.15/kWh power price; a power purchase agreement is expected in Q1 2027.
Funding and execution
The US$400M funding plan assumes US$220M debt and US$180M equity or quasi-equity; discussions with the US DFC cover US$150–170M of senior debt.
Funding is not secured and no lender or investor has committed; the final funding mix remains undetermined, and equity or quasi-equity may substantially dilute shareholders.
A pilot plant using real ore is scheduled to run from November 2026, testing the full flowsheet; the board’s FID decision is targeted for December 2026.
Principal Mauritanian approvals are granted; remaining routine water, power, transport and export permits are expected through 2027.
Construction is planned to start in Q1 2027, with first ore by end-2028 and nameplate production targeted for 2030.
Latest events from Aura Energy
- Tiris advances toward FID with a US$500.3m BFS NPV and 2.04 quarters of cash runway.AEE
Q1 2027 TU - Tiris pilot plant construction and key offtake deals mark progress amid narrowed losses and strong cash.AEE
H2 2026 - Tiris project advances toward production with strong cash reserves and supportive uranium market.AEE
Q4 2026 TU - Tiris and Häggån projects drive near-term uranium growth and leverage global energy transition.AEE
Investor presentation - Tiris project targets 2027 uranium production with 91.3Mlbs resources and strong growth prospects.AEE
Investor presentation - Over 900Mlbs uranium resources, near-term production, and strong market outlook drive growth.AEE
Investor presentation - Tiris resource upgrade and permitting drive project value; cash supports next-stage development.AEE
Q4 2024 TU - Tiris Uranium Project advanced to construction-ready status with major resource and funding milestones.AEE
H2 2024 - Tiris Uranium Project advances to FID with robust economics and full permitting secured.AEE
Q1 2025 TU