BCI Minerals (BCI) Q1 2027 earnings summary
Event summary combining transcript, slides, and related documents.
Q1 2027 earnings summary
20 Oct, 2026Executive summary
Mardie construction reached 90% completion excluding crystalliser lining and 87% including it; the port was 98% complete at quarter-end.
Crystallised salt reached 266,000 tonnes across 12 commissioned cells, as preparations advanced toward first salt on ship in CY2027.
Financial highlights
Construction costs reached $1,265M against an approved $1,443M budget; estimated construction cost to complete was $178M at 30 September 2026.
Cumulative Mardie expenditure reached $1,586M, including $321M in pre-revenue operating expenditure.
Available funds were reported at $316M at quarter-end; cash of $110.3M and undrawn facility capacity of $227.1M were also reported, with total available funds of $337.4M including guarantees.
First construction and working capital were fully funded.
Outlook and guidance
First salt on ship remains targeted for CY2027, with timing dependent on weather, summer evaporation and salt growth.
Salt Wash Plant completion is expected in late CY2026; Pilbara Ports Road upgrade completion is scheduled for early CY2027.
A further 16 crystalliser cells are scheduled for progressive lining through Q4 FY2027 to support ramp-up.
Port construction completion and jetty wet commissioning are planned for CY2027; Mardie Spirit is also scheduled to arrive in CY2027.
SOP pilot commissioning is planned after plant arrival in CY2027, with an expected ~12-month trial; detailed design and procurement are progressing in parallel.
Latest events from BCI Minerals
- First crystallised salt produced as construction nears completion and ramp-up begins.BCI
H2 2026 - Salt project nears completion, targeting 2027 harvest with strong demand and robust financials.BCI
Noosa Mining Conference 2026 - 85% construction complete, 49kt salt crystallised, and first shipment targeted for Q1 2027.BCI
Q4 2026 - Salt ramp-up and construction 81% complete; operations resumed and funding secured.BCI
Q3 2026 - Achieved full-scale operations at Mardie, strong construction progress, and enhanced liquidity.BCI
H2 2025 - Mardie Project advances with robust funding, asset sales, and growing Asian market demand.BCI
H2 2024 - Project 77% complete, fully funded, net loss widens, Iron Valley sale and note conversion boost liquidity.BCI
H1 2026 - Project is 74% complete, fully funded, operations underway, and first dividends targeted for 2029.BCI
AGM 2025 - 56% construction progress, $981M debt secured, Iron Valley divested for up to $72.6M.BCI
H1 2025