AGM 2024 presentation
Logotype for Boab Metals Limited

Boab Metals (BML) AGM 2024 presentation summary

Event summary combining transcript, slides, and related documents.

Logotype for Boab Metals Limited

AGM 2024 presentation summary

29 Jan, 2026

Strategic progress and project milestones

  • Completed Front-End Engineering & Design (FEED) Study for Sorby Hills, improving project economics and confirming robust financial metrics.

  • Secured an agreement to acquire 100% of Sorby Hills, providing full control over the project and future work programs.

  • Identified the potential acquisition of the DeGrussa Process Plant to materially reduce capital expenditure and accelerate construction timelines.

  • Achieved key milestones including securing an option for full project ownership and identifying significant capital reduction opportunities.

  • Advancing toward a final investment decision in mid-2025, with offtake and financing targeted for late 2024.

Sorby Hills project economics and sensitivities

  • FEED Study outlines a pre-production capex of A$264 million, with 66% underpinned by tendered pricing.

  • Project NPV (8%) is A$411 million with a 37% IRR, and average annual EBITDA of A$126 million.

  • Life-of-mine production targets 546kt payable lead and 17.2Moz payable silver over 8.5 years.

  • C1 cash cost is US$0.36/lb payable lead, including a net silver credit of US$0.37/lb.

  • Project NPV is highly sensitive to silver price movements, with operating margin fully leveraged to silver price.

Resource, reserves, and operational details

  • Total resource: 47.3Mt at 3.1% Pb, 0.4% Zn, and 35g/t Ag, with 1,465kt contained lead and 44.5Moz contained silver.

  • Ore reserve: 15.2Mt at 3.5% Pb and 39g/t Ag, underpinned 83% by measured and indicated resources.

  • Annual production averages 103kt lead-silver concentrate, 64kt lead, and 2.0Moz silver.

  • Operating costs are competitive, with 80% of mining costs underpinned by tendered pricing.

  • Project is considered a low-cost silver producer, with costs covered by historically stable lead prices.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more