Boab Metals (BML) Q4 2024 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q4 2024 TU earnings summary
29 Jan, 2026Executive summary
Completed Front End Engineering (FEED) Study for Sorby Hills Lead-Silver-Zinc Project, confirming strong project economics and technical optimizations.
FEED Study delivered a pre-tax NPV of A$411M, IRR of 37%, and average annual EBITDA of A$126M, with further upside at spot prices.
Raised A$5.0M via placement and entitlement offer to support project advancement and exploration.
Cash balance at 30 June 2024 was approximately A$5.7M.
Financial highlights
FEED Study base case: NPV8 of A$411M, IRR 37%, average annual EBITDA A$126M, net cash flow A$778M.
Spot case (May 2024): NPV8 of A$596M, IRR 47%, average annual EBITDA A$160M, net cash flow A$1,067M.
Upfront capital expenditure increased to A$264M; sustaining capex A$26M.
C1 cost reduced to US$0.36/lb payable lead (including silver credits).
Operating cash flow over life of mine projected at A$1,069M.
Outlook and guidance
Final investment decision targeted for December 2024; first ore expected December 2026, first concentrate shipment March 2027.
Offtake agreement negotiations ongoing, with updates expected in the September quarter.
Phase VIII drilling program planned to expand mineralisation at the 'Keep' target.
Latest events from Boab Metals
- Reduced FY24 loss, improved project economics, and full ownership option set up for FID in FY25.BML
H2 202429 Jan 2026 - Sorby Hills targets near-term production with strong silver leverage and first quartile costs.BML
Corporate presentation29 Jan 2026 - Sorby Hills offers a large, low-cost, silver-leveraged resource nearing production.BML
Corporate presentation29 Jan 2026 - Option secured for 100% Sorby Hills ownership; strong project economics and cash of A$4.35M.BML
Q1 2025 TU29 Jan 2026 - Low-cost, high-grade lead-silver project targets 2025 FID with strong economics and Trafigura backing.BML
Corporate presentation29 Jan 2026 - FEED Study confirms strong economics and full project control, with silver price driving upside.BML
AGM 2024 presentation29 Jan 2026 - US$30M Trafigura deal, EPA approval, and strong cash position advance Sorby Hills toward FID.BML
Q2 2025 TU29 Jan 2026 - Advancing a high-margin, low-cost lead-silver project with strong silver price leverage in WA.BML
Corporate presentation29 Jan 2026 - Sorby Hills targets low-cost, high-margin silver-lead production with strong project economics.BML
Corporate presentation29 Jan 2026