Boab Metals (BML) H2 2026 earnings summary
Event summary combining transcript, slides, and related documents.
H2 2026 earnings summary
2 Oct, 2026Executive summary
Sorby Hills reached FID, construction began in March 2026, and the project is targeting first ore in H2 2027.
The year included acquisition of Yuguang’s remaining 25% interest, making Sorby Hills wholly owned, plus a caravan park acquisition to support workforce accommodation.
Financial highlights
Revenue was $2.237m versus $174,312 in FY25; loss before tax was $7.384m versus $3.841m, and net loss was $7.222m versus $3.841m.
Basic and diluted loss per share was 1.66 cents versus 1.63 cents in FY25; adjusted for the $2.797m derivative fair-value loss, reported pre-tax loss was $7.384m.
Cash and cash equivalents were $60.862m at 30 June 2026 versus $7.529m; operating cash outflow was $1.612m and investing cash outflow was $45.788m.
Total assets reached $156.047m versus $16.538m; equity was $121.374m versus $15.790m at FY25 end.
Outlook and guidance
First ore is targeted for H2 2027; forecasts assume debt drawdown in Q4 2026 and delivery, commissioning, production ramp-up and sales broadly to schedule and budget.
The September 2026 Sorby Hills Project Delivery Plan estimated total capex of $262m, with $205m remaining to spend, incorporating contracted costs to date.
Directors expect available cash, planned drawdown of the A$236m facility and forecast cash flows to fund requirements for at least 12 months from report signing, subject to forecast assumptions and funding conditions.
Latest events from Boab Metals
- Fully funded project targets 2027 production with extended mine life and strong economics.BML
Mining Forum Americas 2026 - Construction of a major silver-lead project is underway, targeting production in H2 2027.BML
Corporate presentation - Sorby Hills project advances on schedule with robust funding and key contracts secured.BML
Q4 2026 TU - Advanced Sorby Hills toward FID with key milestones, improved cash, and robust project economics.BML
H2 2025 - Sorby Hills project advances with improved economics, reduced loss, and path to 100% ownership.BML
H2 2024 - Sorby Hills fully funded and construction underway, with cash reserves at $89.9 million.BML
H1 2026 - FEED Study shows strong project economics, reduced costs, and solid funding position.BML
Q4 2024 TU - Sorby Hills targets near-term production with strong silver leverage and first quartile costs.BML
Corporate presentation - Sorby Hills offers a large, low-cost, silver-leveraged resource nearing production.BML
Corporate presentation