Boab Metals (BML) Mining Forum Americas 2026 summary
Event summary combining transcript, slides, and related documents.
Mining Forum Americas 2026 summary
30 Sep, 2026Project Overview and Financials
Achieved 100% project ownership and secured AUD 350 million in funding, with all permits and offtake agreements in place.
Project NPV stands at AUD 1.06 billion with a 97% IRR, and only AUD 205 million remains to complete construction.
Mine life extended to 10.5 years, supported by a Mineral Resource of 50.6Mt and ongoing reserve growth.
Capital costs reduced by AUD 20 million and construction timeline shortened by six months through acquisition of the DeGrussa process plant.
Construction is on track for wet commissioning in June next year, targeting full production by late Q3 or H2 2027.
Operational Highlights and Market Positioning
Near-surface, open-pit ore body enables low-risk, low-cost mining, with two-thirds of reserves now proven.
Annual production forecast at over 2.2 million ounces of silver and nearly 70,000 tonnes of lead, making it the fourth-largest silver producer in Australia.
Lead production covers all operating costs, providing strong exposure to silver price upside; all-in sustaining cost is about AUD 8.70/oz.
Benefiting from tight silver-lead concentrate markets and record low treatment charges, with flexible offtake arrangements.
Diesel supply secured at discounted rates, with plans to transition to clean hydropower within 12 months of production start.
Growth Strategy and Future Outlook
Ongoing drilling and resource expansion expected to further extend mine life beyond 10.5 years, with only 37% of the defined resource included in the current mine plan.
Competitive tender underway for remaining offtake to lock in favorable terms and maximize cash flow.
Exploration focus on nearby Manbarrum Project and areas south of Sorby Hills for additional resource growth.
80% of project costs are locked in, providing strong cost certainty as construction progresses.
Multiple near-term catalysts identified, including resource growth, completion of plant relocation, and ore body exposure.
Latest events from Boab Metals
- Sorby Hills construction is underway, with first ore targeted for H2 2027 and $60.9m cash on hand.BML
H2 2026 - Construction of a major silver-lead project is underway, targeting production in H2 2027.BML
Corporate presentation - Sorby Hills project advances on schedule with robust funding and key contracts secured.BML
Q4 2026 TU - Advanced Sorby Hills toward FID with key milestones, improved cash, and robust project economics.BML
H2 2025 - Sorby Hills project advances with improved economics, reduced loss, and path to 100% ownership.BML
H2 2024 - Sorby Hills fully funded and construction underway, with cash reserves at $89.9 million.BML
H1 2026 - FEED Study shows strong project economics, reduced costs, and solid funding position.BML
Q4 2024 TU - Sorby Hills targets near-term production with strong silver leverage and first quartile costs.BML
Corporate presentation - Sorby Hills offers a large, low-cost, silver-leveraged resource nearing production.BML
Corporate presentation