Bunker Hill Mining (BNKR) Corporate presentation summary
Event summary combining transcript, slides, and related documents.
Corporate presentation summary
21 Jan, 2026Project development and operational progress
Restart project is 70% complete, targeting first production in H1 2026 at 1,800 tpd, with expansion to 2,500 tpd planned and $150M EXIM support secured.
Processing plant is 88% complete, with final electrical and piping installation ongoing; tailings filter plant is 56% complete.
Fully permitted site with 98% procurement concluded, leveraging existing infrastructure and low-cost power.
Clean zinc and lead/silver concentrates will be trucked to Teck's Trail Smelter, with >80% metal recovery rates.
Mine is positioned for low-cost mechanized underground mining, with significant optimization opportunities.
Resource base, expansion, and exploration
Large mineral endowment with consistent reserve replacement over 90 years and a 5-year initial mine life per 2022 PFS.
Expansion plan aims to extend mine life and restore a 50/50 silver-base metals revenue mix, with significant increases in free cash flow as more silver is produced.
Measured and indicated resources total 7.0 Mt, with an additional 6.9 Mt inferred; probable reserves stand at 3.2 Mt.
Substantial exploration upside remains, with the deposit open at depth and most of the 2,300 ha land package underexplored.
Recent surveys have defined several high-priority targets for further drilling and resource growth.
Financials, capital structure, and peer positioning
Strong support from strategic partners, including Teck (32% ownership), Sprott, and retail investors.
Total debt outstanding is $76M, with $44M in total liquidity and $34M cash on hand as of January 2026.
Well-positioned for a valuation re-rating upon achieving production, with peer comparisons showing significant upside.
Expansion to 2,500 tpd projected to lower AISC to $0.60/lb Zn payable and increase annual AgEq production by 36%.
Funding for expansion includes a $150M US EXIM Bank LOI, supporting rapid development and job creation.
Latest events from Bunker Hill Mining
- On track for 2026 production with major expansion, strong financials, and significant exploration upside.BNKR
Corporate presentation16 Mar 2026 - Net loss narrowed as mine restart advanced, with major financing secured and commissioning set for year-end.BNKR
Q2 202421 Jan 2026 - Q3 2024 saw a net loss, increased liabilities, and major financing to support mine development.BNKR
Q3 202421 Jan 2026 - Mine restart delayed to 2026, net loss widens, and urgent financing is needed for project viability.BNKR
Q4 202421 Jan 2026 - Net loss increased to $6.35 million in Q1 2025 amid ongoing mine development and financing challenges.BNKR
Q1 202521 Jan 2026 - Q2 2025 net income surged to $20.5M after a major debt-equity restructuring and stream settlement.BNKR
Q2 202521 Jan 2026 - Major financings and debt restructuring improved liquidity as mine restart targets 2026.BNKR
Q3 202521 Jan 2026