Bunker Hill Mining (BNKR) Corporate presentation summary
Event summary combining transcript, slides, and related documents.
Corporate presentation summary
8 May, 2026Project status and development
Project is 90% complete and on track for first production in H1 2026, with phased commissioning underway.
Expanded land package now totals 6,283.7 acres, making it the largest in the Silver Valley.
Processing plant and tailings filter plant construction are progressing, with commissioning scheduled before production.
The 1,800 tpd processing facility is over 90% complete and designed for future expansion to 2,500 tpd.
Bunker 2.0 expansion targets 2,500 tpd throughput, supported by a $150M US EXIM Bank LOI.
Operational advantages and cost structure
Located in a premier US mining jurisdiction with 100% private land and 406 patented claims.
Portal access to shallow mineralization enables low-cost, mechanized underground mining.
Low-cost power ($0.06/kWh), highway access, and proximity to Trail Smelter reduce logistics costs.
Positioned on the lower half of the zinc cost curve, with significant optimization opportunities.
In-house mining, legacy infrastructure, and supportive community contribute to cost efficiency.
Resource base and expansion potential
Measured & Indicated resources: 7.0 Mt @ 1.00 opt Ag, 2.40% Pb, 5.44% Zn; Inferred: 6.9 Mt @ 1.52 opt Ag, 2.87% Pb, 4.96% Zn.
Probable reserves: 3.2 Mt @ 1.12 opt Ag, 2.59% Pb, 5.81% Zn.
Expansion plan aims to extend mine life and restore a 50/50 silver-base metals revenue mix.
Significant increase in free cash flow projected as higher-grade silver is mined in later years.
Substantial exploration upside with most of the 2,300-hectare land claim package underexplored.
Latest events from Bunker Hill Mining
- Q1 2026 net income surged to $20.1M on warrant revaluation gains, with no revenue reported.BNKR
Q1 20267 May 2026 - On track for 2026 production, major expansion, and strong growth potential in a top mining district.BNKR
Corporate presentation1 May 2026 - C$0.15/unit private placement raises $26M+ for mine restart, with Teck and Sprott as lead investors.BNKR
Registration Filing18 Mar 2026 - Major restructuring, $61.8M raised, and mine restart targeted for H1 2026 amid $93.1M net loss.BNKR
Q4 202518 Mar 2026 - Net loss widened to $25.3M in 2024; mine restart delayed to 2026 pending major new financing.BNKR
Q4 202418 Mar 2026 - Major mine restart planned for 2026 after significant 2025 recapitalization and equity raises.BNKR
Registration Filing18 Mar 2026 - Proxy covers director elections, compensation, equity plans, and major 2024 milestones.BNKR
Proxy Filing18 Mar 2026 - Restart-focused mining company advances toward 2026 production after major recapitalization.BNKR
Registration Filing18 Mar 2026 - On track for 2026 production with major expansion, strong financials, and significant exploration upside.BNKR
Corporate presentation16 Mar 2026