29 Sep, 2026Strategic growth and asset portfolio
Targeting production increase from 75,000 to over 200,000 ounces annually by 2029, driven by a diversified portfolio of four assets in Zimbabwe.
Blanket Mine, acquired in 2006, has grown its resource base from 60,000 to nearly 3 million ounces and currently produces 70,000–75,000 ounces per year.
Recent initiatives at Blanket include a 7-day work week and new oxide resource commercialization, expected to boost annual output to nearly 90,000 ounces.
Bilboes, the immediate development focus, was acquired in 2023 and holds 2.5 million ounces M&I at 2.3 g/t, with first gold production targeted for late 2028 and full production in 2029.
Motapa, adjacent to Bilboes, recently announced a maiden resource of over 500,000 ounces, supporting future production smoothing.
Financial performance and stakeholder value
Over the past decade, more than $250 million has been distributed to Zimbabwean stakeholders, including government, workers, and the community.
Shareholder returns have reached approximately 1,200% over 10 years, outperforming sector benchmarks and gold itself.
Blanket Mine's cash generation supports dividends, head office costs, and contributes to funding new projects.
The company has maintained quarterly dividend payments since 2012.
Bilboes project economics and funding
Bilboes project has an NPV of over $1.5 billion at a $4,000/oz gold price, with an ungeared post-tax IRR near 60% and an 11-year mine life.
All-in sustaining cost is about $1,145/oz, yielding around $3,000/oz profit at current prices; first full year of production expected to generate $600 million in disposable cash, tax-free.
Peak funding requirement is $484 million, with a payback period of less than one year.
Funding strategy includes gold price hedging, a $150 million convertible note (four times oversubscribed), $150 million from Zimbabwean banks, and a planned $300–350 million project finance facility.
As of end Q2, $172 million cash on hand and $13 million in bullion provide strong liquidity for project initiation.
Latest events from Caledonia Mining
- Gold output to reach approximately 280,000 ounces by 2029, led by Bilboes and Blanket growth.CMCL
CMD 2026 - Gold production and profit rose sharply, with strong liquidity and key projects advancing.CMCL
Q2 2026 - Higher gold prices drove strong profit and cash flow despite lower production and higher costs.CMCL
Q1 2026 - Multi-asset gold growth strategy leverages strong assets, ESG focus, and Zimbabwean expansion.CMCL
Corporate presentation - Record revenue and profit growth in FY 2025, with robust cash flow and major growth projects.CMCL
Q4 2025 - Revenue and EBITDA surged on higher gold prices, with costs and exploration both rising.CMCL
Q3 2025 - Revenue and gross profit rose, but net profit fell due to higher costs and FX losses.CMCL
Q3 2024 - Single-phase project targets 1.5Moz gold, $309M NPV, 34% IRR, and 1.9-year payback.CMCL