16 Oct, 2026Executive summary
Consolidated revenue rose 14.5% YoY to R$2.978bn; EBITDA increased 20.3% to R$550.2m and net income rose 8.9% to R$252.7m.
Revenue excluding construction revenue increased 14.4% to R$2,739m; billed energy rose 5.0% to 8,195 GWh.
Higher electricity demand and tariff-related revenue supported growth, while rising energy costs, doubtful-account provisions and financing expenses weighed on results.
KPMG’s interim review found no indication that the financial information was materially non-compliant with CPC 21 (R1) and IAS 34.
Financial highlights
Gross operating revenue rose 12.4% YoY to R$4.631bn; operating costs and expenses increased 13.1% to R$2.535bn and EBIT rose 16.5% to R$377.7m.
Gross profit reached R$620.9m, up from R$525.1m; earnings before financial result and taxes were R$459.0m, versus R$373.7m.
Financial result was negative R$81.3m versus negative R$49.5m; income tax and social contribution expense rose to R$125.1m from R$92.1m.
Cash and equivalents were R$755.3m at quarter-end, down from R$1.019bn at year-end; operating cash flow was R$31.2m versus R$239.0m in 1Q24.
Outlook and guidance
Collection actions were planned to resume gradually from April through July 2025, first in selected municipalities and then statewide, following commercial-system stabilization.
Planned investments include ~R$70m for the Caveiras expansion and ~R$240m for Salto Weissbach, with part of its funding expected from BNDES.
A five-year climate resilience and sustainability program is scheduled to begin in 2026, with investments exceeding US$305m, including US$243m of planned IDB financing.
A R$4.5bn electricity-sector investment plan was outlined through 2026; the EV charging corridor expansion targets 100 municipalities in 2025, with planned investment above R$5m.
Rio Bonito construction and Cedros and Pinhal development are planned to advance through environmental, regulatory and design work in 2025.
Latest events from Centrais Elétricas de Santa Catarina
- Higher billed energy and investment, but lower earnings amid tariff and financing pressures.CLSC4
Q1 2023 - 2Q23 profit surged as distribution gains outweighed weaker generation.CLSC4
Q2 2023 - 9M earnings grew, while financing costs and lower generation pressured Q3 profit.CLSC4
Q3 2023 - FY23 earnings grew, while Q4 provisions weighed on results and net debt increased.CLSC4
Q4 2023 - Profit and EBITDA grew as billed electricity rose 6.6%, despite lower hydropower output.CLSC4
Q1 2024 - Q2 earnings rose on stronger demand, while billing-system issues disrupted collections.CLSC4
Q2 2024 - 9M24 earnings rose as collection disruption and higher debt remained key risks.CLSC4
Q3 2024 - FY24 EBITDA rose 37.51% as demand and infrastructure investment strengthened.CLSC4
Q4 2024 - Revenue grew, but higher costs and financial pressure cut Q2 earnings.CLSC4