Centrais Elétricas de Santa Catarina (CLSC4) Q4 2024 earnings summary
Event summary combining transcript, slides, and related documents.
Q4 2024 earnings summary
16 Oct, 2026Executive summary
FY24 consolidated revenue was R$10.66bn (+2.46% YoY), net income R$715.8m (+28.5%) and EBITDA R$1.567bn (+37.51%).
Adjusted FY24 EBITDA was R$1.50bn (+10.6%); adjusted net income was R$673.8m (-4.0%).
Higher electricity demand and infrastructure investment supported results; the financial result weakened as debt costs and debenture expenses increased.
Financial highlights
4Q24 consolidated revenue was R$2.81bn (+3.4% YoY), EBITDA R$327.9m (+174.7%) and net income R$130.1m (+46.2%).
FY24 operating costs and expenses fell 1.3% to R$9.50bn; net operating revenue excluding construction revenue rose 2.8% to R$9.67bn.
Construction revenue was R$985.7m in FY24 (-1.2%); adjusted EBITDA excluding construction revenue was R$1.50bn.
Gross profit reached R$1.81bn vs. R$1.66bn in 2023; EBIT was R$1.22bn, up 47.83%.
Financial result was a R$287.4m loss vs. a R$141.8m loss; operating cash flow was R$281.7m vs. R$450.3m.
Outlook and guidance
Approved retail energy-market plan includes an AI-based simulator to identify customer profiles, potential margins and savings.
2025 electric-vehicle charging rollout targets 100 municipalities, with more than R$5M planned investment and stations targeted at intervals up to 50 km where feasible.
Approved 2025 consolidated investment budget totals R$1.448bn, including R$1.326bn for distribution and R$122.5m for generation; a further R$262.3m in distribution investment is planned using ICMS Agreement funds.
Planned system improvements are expected to reach R$4.5bn by end-2026; 2025 generation plans include Caveiras and Salto Weissbach expansion projects.
Commercial-system issues affecting collections are expected to be resolved by mid-2025; corrective measures are underway.
Latest events from Centrais Elétricas de Santa Catarina
- Higher billed energy and investment, but lower earnings amid tariff and financing pressures.CLSC4
Q1 2023 - 2Q23 profit surged as distribution gains outweighed weaker generation.CLSC4
Q2 2023 - 9M earnings grew, while financing costs and lower generation pressured Q3 profit.CLSC4
Q3 2023 - FY23 earnings grew, while Q4 provisions weighed on results and net debt increased.CLSC4
Q4 2023 - Profit and EBITDA grew as billed electricity rose 6.6%, despite lower hydropower output.CLSC4
Q1 2024 - Q2 earnings rose on stronger demand, while billing-system issues disrupted collections.CLSC4
Q2 2024 - 9M24 earnings rose as collection disruption and higher debt remained key risks.CLSC4
Q3 2024 - Revenue, EBITDA and net income grew, but billing disruption and higher costs weighed on cash generation.CLSC4
Q1 2025 - Revenue grew, but higher costs and financial pressure cut Q2 earnings.CLSC4
Q2 2025