Gonneville project

  • Resource totals 17Moz 3E, 960kt Ni, 540kt Cu and 96kt Co; maiden Ore Reserve is 260Mt containing 7.1Moz 3E.

  • PFS base case projects pre-tax NPV8 of A$1.4bn, 23% IRR and ~2.7-year payback; pre-production CapEx is A$820M.

  • Initial 23-year open-pit phase targets average annual output of 220koz 3E, 7kt Ni, 8kt Cu and 0.7kt Co; forecast AISC is US$370/oz 3E.

  • Feasibility Study is underway for Stage 1 at 5Mtpa, with completion targeted for H2 CY27; FID is targeted for H1 CY28 and first production for 2030.

  • ~7.9Moz 3E, 450kt Ni, 250kt Cu and 46kt Co sit below the PFS pit shell, supporting potential deeper open-pit mining or an eventual underground transition.

Funding and execution

  • Funding strategy targets senior debt for 60–70% of pre-production CapEx, or ~A$500–600M, mainly from export credit agencies; long tenors and competitive rates are anticipated.

  • Strong inbound interest in Cu and Ni concentrate offtake; offtake-linked financing, government grants and other debt or royalty options are under consideration.

  • An ~8-week full-flowsheet pilot is processing ~5 tonnes of fresh sulphide ore; completion is scheduled for Q1 CY27, with results intended to inform processing parameters and offtake samples.

  • Environmental Review Documents are being prepared for H2 CY26 submission; the project has WA Strategic Project and Commonwealth Major Project status.

  • ~A$270M has been invested in development; ~A$53M in cash and liquid investments was held at 30 September 2026.

Kestrel copper-gold discovery

  • First discovery hole WCRC001 returned 15m at 8.6g/t Au and 0.54% Cu from 78m, within 27m at 4.8g/t Au and 0.42% Cu.

  • Copper was intersected in all six holes; ~500m of a ~2.2km interpreted trend has been tested, with mineralisation open in all directions.

  • Follow-up work includes pending assays for eight holes, a ground gravity survey and step-out RC drilling; Pan African is evaluating a Warrego processing hub ~20km away.