Challenger Gold (CEL) JMM Gold Forum 2026 summary

Event summary combining transcript, slides, and related documents.

Logotype for Challenger Gold Limited

JMM Gold Forum 2026 summary

30 Sep, 2026

Project portfolio and exploration

  • Hualilán in Argentina is the flagship, fully permitted, and advanced from exploration to execution after a PFS in May 2026, with a 14.25-year mine life and production averaging 135 koz/year after year 2.

  • El Guayabo in Ecuador holds 9.1 million AuEq ounces, with 6.9 million attributable, and strong exploration potential remains open at depth and on strike.

  • Located near a major project sold for AUD 650 million, El Guayabo's exploration plan is being developed, with updates expected next year.

  • Exploration and reserve growth targeted through a 35,000m drilling campaign, aiming to expand resources, convert to reserves, and optimize the mine plan.

Development strategy and operational plans

  • Hualilán will start with heap leach operations in 2029, followed by a flotation circuit, targeting a 14-year mine life.

  • Staged CapEx allows initial heap leach build in two years, with flotation funded from cash flow, reducing operational risk.

  • Bulk open pit mining and conventional methods are planned, with a 1.5 million ton/year flotation circuit.

  • Staged, capital-efficient development with initial capex of $267M ($232M excluding contingency), leveraging existing infrastructure and government support.

  • Multiple opportunities identified to enhance project value, including increased throughput, higher recovery rates, and third-party financing for infrastructure.

Financials and value creation

  • Hualilán's feasibility study includes RIGI system benefits, adding $185 million to NPV; total CapEx is $267 million, with $48 million for a third-party-built power line.

  • Project NPV is $1.1 billion at $3,500/oz gold and $1.8 billion at $4,500/oz, with a 35% return and payback in 1.25–2.25 years.

  • Removal of Inferred Mineral Resources from the mine plan still yields a positive NPV and IRR, though with a reduced mine life.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more

Latest events from Challenger Gold