Challenger Gold (CEL) Q4 2025 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q4 2025 TU earnings summary
2 Jun, 2026Executive summary
Mining at Hualilan commenced on schedule and exceeded production forecasts, with 175,229 tonnes mined in December versus a forecast of 146,316 tonnes.
Ore haulage to Casposo for toll processing is set to begin mid-February 2026, with processing to follow 2-4 weeks later.
The Casposo plant restart has delivered gold recoveries above 90%.
The Hualilan Pre-Feasibility Study (PFS) is on track for completion in Q1 2026, with open pit design and scheduling finalized.
Ecuador projects' Mineral Resource Estimate (MRE) doubled to 9.1 Moz AuEq, enhancing regional significance.
Financial highlights
Cash at quarter-end was $36.2 million, fully funding operations through to first toll milling cash flow.
Quarterly expenditure included A$12.8 million in one-off costs: A$5.1 million for contractor mobilisation, A$3.0 million in toll milling capex, A$1.8 million in capital raise fees, and A$3 million project finance repayment.
Exploration and development expenditure totaled $3.1 million, down from $3.9 million in the previous quarter.
Administration and corporate costs were $1.33 million, up from $1.2 million last quarter, including $0.59 million in interest on convertible notes.
Outlook and guidance
Ore haulage and processing at Casposo are expected to commence as scheduled, with full-scale operations ramping up.
The PFS financial model and capital cost estimate are nearing completion, with finalization expected in February 2026.
Underground mining potential at Hualilan will be reassessed after further drilling over the next 12-18 months.
Monetisation options for Ecuador assets are being explored, including TSX listing, sale, or partnership.
Latest events from Challenger Gold
- Toll processing and gold sales to commence in May 2026, with strong mining and resource growth.CEL
Q1 2026 TU - Hualilan PFS highlights strong economics and scale, with capital raise and leadership changes supporting growth.CEL
Q2 2026 TU - Fully funded transition to production with robust economics, long mine life, and major upside.CEL
Investor update - Hualilan PFS advances with expanded open pit; Ecuador drilling delivers strong gold-copper results.CEL
Q2 2024 TU - Transitioned to gold production, raising $70M+ and doubling Ecuador resources, but faces going concern risk.CEL
H2 2025 - Net profit surged 38% to $74.6M, with Hualilan advancing and funding secured for growth.CEL
H2 2024 - Hualilan toll milling fully permitted and set for January 2026 start; Ecuador resources doubled.CEL
Q3 2025 TU - Half-year profit reached $7.26M, with major capital raised and Hualilan PFS confirming strong economics.CEL
H1 2025 - Toll Milling launch and Heap Leach unlocks drive growth, with asset sale poised to boost value.CEL
Noosa Mining Investor Conference