Deep Fission (FISN) Registration filing summary
Event summary combining transcript, slides, and related documents.
Registration filing summary
4 Nov, 2026Company overview and business model
Early-stage nuclear technology platform based on established PWR technology; Gravity Reactor places reactors in boreholes ~1 mile underground, using water-column pressure for operating pressure and cooling and surrounding geology for confinement and shielding.
Each 3x3 reactor targets up to 15 MWe; standalone or clustered deployments are designed to scale to hundreds or potentially thousands of MWe per site.
Phased plan: validate drilling and emplacement, pursue DOE authorization and pilot wells, then seek high-volume commercial licensing for clustered and multi-site deployment.
Kansas Site includes a long-term lease for ~100 acres; first data well reached 6,000 feet, and a full-size prototype canister was lowered into and retrieved from a 34-inch borehole in September 2026.
IP portfolio includes issued patents and pending applications covering reactor configuration, underground emplacement, drilling, casing, thermal-hydraulic performance, instrumentation and monitoring.
Financial performance and metrics
Development-stage operations; no commercial reactor constructed or operated and no revenue generated to date.
A 150 MW Master Energy Purchase Agreement with Great Plains Development Authority targets commercial operation in September 2028; initial 5 MWe deployment is a separate plan.
Use of proceeds and capital allocation
Net proceeds from future security sales are designated for purposes to be specified in the applicable prospectus supplement.
Near-term development priorities include proof-of-concept wells, reactor design and safety analysis, site work, and delivery of casing, reactor canister and heat exchanger components, plus low-enriched uranium fabrication and loading.
Latest events from Deep Fission
- Development spending surged, but current liquidity falls short of the funding runway needed.FISN
Q3 2026 - Great Plains targets a 5 MWe pilot in 2027, 150 MW in 2028 and potential expansion to 2,000 MW.FISN
Status update - Underground borehole reactors promise fast, safe, and scalable nuclear power by 2027.FISN
EnerCom Denver – The Energy Investment Conference - Underground reactor targets rapid, scalable, and secure zero-carbon power for data centers and industry.FISN
Corporate presentation - Deep borehole nuclear reactors promise fast, safe, and scalable clean energy deployment.FISN
Canaccord Genuity's 46th Annual Growth Conference - Underground PWR technology targets rapid, secure, and scalable power for data centers by 2027.FISN
Corporate presentation - Net loss surged to $31M in Q2 2026; additional capital needed to sustain operations.FISN
Q2 2026 - Shareholders will vote on director elections, auditor ratification, and expanding the equity plan.FISN
Proxy filing - Pre-revenue nuclear SMR developer seeks IPO to fund pilot, faces high risk and major capital needs.FISN
Registration filing