Deep Yellow (DYL) Q1 2027 TU earnings summary

Event summary combining transcript, slides, and related documents.

Logotype for Deep Yellow Limited

Q1 2027 TU earnings summary

27 Oct, 2026

Executive summary

  • Tumas development advanced, but FID was deferred from Q4 2026 because equity market conditions did not support proceeding; commitment to the project remains.

  • Quarter-end cash was A$144.7 million, supporting continued staged development and portfolio advancement.

Financial highlights

  • Cash and cash equivalents were A$144.7 million at 30 September 2026, down from A$160.0 million at 30 June 2026.

  • Development expenditure was A$7.6 million, primarily for Tumas; exploration and evaluation expenditure was A$4.6 million across Namibia and Australian projects.

  • No mining production activities occurred during the quarter.

Outlook and guidance

  • A comprehensive Tumas project update, including revised execution and mining schedules, capital and operating costs, and financial model, is expected once optimisation work is complete.

  • Water pipe supply contract award is expected before end-2026; a tender for pipeline installation is expected in Q1 2027.

  • Revised Mulga Rock study work remains on schedule; first product is planned approximately two years after Tumas production commences.

  • S-Bend drilling was scheduled to begin in October 2026; Mulga Rock hydrogeological drilling is planned for Q1 2027, followed by pumping tests in Q2 2027.