Deep Yellow (DYL) Q2 2026 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q2 2026 TU earnings summary
22 Jan, 2026Executive summary
Staged development of the Tumas Project in Namibia is advancing, with detailed engineering over 60% complete and bulk earthworks 24% finished as of December 2025.
Power supply agreement executed and independent technical due diligence completed, supporting project debt financing for Tumas.
Exploration at the Tinkas Prospect adjacent to Tumas identified uranium mineralisation up to 11m thick from surface.
Mulga Rock Project in Western Australia progressed with trade-off studies and completion of ground gravity and passive seismic surveys.
Alligator River Project in Northern Territory completed 4,660m of drilling, identifying significant hydrothermal alteration at the Q14 anomaly.
Group cash balance at 31 December 2025 was A$187.1 million.
Leadership transition underway, with new CEO and Managing Director appointments effective early 2026.
Financial highlights
Cash balance decreased to A$187.1 million from A$203.5 million in the previous quarter.
A$14.0 million spent on Tumas development and A$4.1 million on exploration and evaluation activities during the quarter.
No mining production activities conducted during the quarter.
Outlook and guidance
Tumas Project is being prepared for a final investment decision, pending supportive uranium market conditions.
Mulga Rock Project aims for first product approximately two years after Tumas commences production.
Uranium market outlook remains strong, with spot and term prices rising and global demand expected to increase.
Latest events from Deep Yellow
- Net loss increased as uranium project development advanced; strong cash reserves maintained.DYL
H1 20265 Mar 2026 - Innovative uranium projects and strong market demand position for long-term, low-cost growth.DYL
Diggers & Dealers Mining Forum 202523 Nov 2025 - Tumas and Mulga Rock projects advance on schedule amid strong cash reserves and bullish uranium outlook.DYL
Q1 2026 TU22 Oct 2025 - Tumas and Mulga Rock projects progress on schedule, supporting a robust financial position.DYL
Q4 2025 TU23 Jul 2025 - Flagship project FID deferred; robust economics, strong cash, and staged development continue.DYL
Q3 2025 TU22 Jun 2025 - Tumas and Mulga Rock projects target over 7 Mlb uranium output annually by 2028.DYL
Company Presentation18 Jun 2025 - Surging nuclear demand and supply constraints position the company for major uranium growth.DYL
Corporate Presentation18 Jun 2025 - Tumas mining licence, $250M raise, and resource upgrades position Deep Yellow for growth.DYL
H2 202413 Jun 2025 - Deep Yellow is set to become a top uranium producer as global supply struggles to meet demand.DYL
Company Presentation6 Jun 2025