Deep Yellow (DYL) Q4 2025 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q4 2025 TU earnings summary
23 Jul, 2025Executive summary
Advanced engineering, procurement, and operational planning at the Tumas Project, with 92% of direct capital procurement well-advanced and early site works largely completed.
Mulga Rock Project completed a successful 3-month resin mini-pilot study, confirming effective separation of uranium and critical minerals, supporting a revised DFS now underway.
Group cash balance stood at A$217.4M at quarter end, reflecting a strong financial position.
Financial highlights
Group cash balance at 30 June 2025 was A$217.4M.
Expected receipts of approximately A$9.5M in FY26 from R&D refund, VAT refunds, and loan repayments.
Quarterly development spend: A$6.5M at Tumas; A$2.9M on exploration at Mulga Rock and Alligator River.
Payments to related parties and associates totaled approximately A$685K for the quarter.
Outlook and guidance
Tumas Project progressing toward final investment decision, with operational readiness and major contracts advancing.
Mulga Rock revised DFS expected to complete in Q3 CY2026, incorporating updated process flowsheet and ORE.
Alligator River Project field programs and government co-funding grants to support exploration in H2 CY2025.
Latest events from Deep Yellow
- Tumas Project nears FID as engineering milestones achieved and uranium market outlook strengthens.DYL
Q4 2026 TU - Ready to deliver multi-decade uranium production with robust assets, team, and market positioning.DYL
Corporate presentation - Tumas and Mulga Rock projects advanced, cash strong, uranium prices up, exploration positive.DYL
Q3 2026 TU - Returned to profitability with $7.16M net profit, strong cash, and staged uranium project development.DYL
H2 2025 - $250M equity raise, Tumas licence granted, and resource upgrades drive growth despite FY24 loss.DYL
H2 2024 - Net loss increased as uranium project development advanced; strong cash reserves maintained.DYL
H1 2026 - Tumas Project advances, exploration yields results, and cash remains strong at A$187.1 million.DYL
Q2 2026 TU - Tumas and Mulga Rock projects advance on schedule amid strong cash reserves and bullish uranium outlook.DYL
Q1 2026 TU - Innovative uranium projects and strong market demand position for long-term, low-cost growth.DYL