Executive summary

  • 2026 first-pass drilling completed across four Nabarlek targets: 40 holes for 11,050m, with uranium intersections at Nabarlek North and Big Radon and strong alteration at KP.

  • Exploration focus is moving to target refinement for 2027; quarter-end cash was $21.7m, supplemented by listed and unlisted investments.

Financial highlights

  • Exploration and evaluation expenditure was $5.055m for the quarter; administration costs, including staff, were $568,026.

  • Cash and cash equivalents were $21.698m at 30 September 2026, versus $27.171m at quarter start; cash from operations was negative $5.290m.

  • Interest received was $336,000; investing cash outflow was $152,000 and financing cash outflow was $31,000.

  • A 21.63% Lachlan Star holding had a market value of $8.8m at quarter end; an additional 4.04% interest was held in unlisted entX.

Outlook and guidance

  • Results and datasets are being analysed to prioritise higher-probability drill targets for the 2027 campaign.

  • Hyperspectral survey results will guide priority field mapping and pathfinder sampling before drill targeting; broader survey review is continuing.

  • Access to Mustang and Junction targets is anticipated over the next 12 to 18 months, following completed anthropological surveys and negotiations on access agreements.

  • Murphy West drilling is subject to approval; Caramal drill permit applications remain awaiting approval.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more

Latest events from DevEx Resources